A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
  • a)
    18 days
  • b)
    27 days
  • c)
    26.67 days
  • d)
    16 days
  • e)
    12 days
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
A can complete a project in 20 days and B can complete the same projec...
Understanding the Problem
To solve this problem, we need to understand the individual work rates of A and B, and how their combined work rate changes when A quits 10 days before the project is completed.

Solving the Problem
1. Work Rates of A and B:
- A completes the project in 20 days, so A's work rate is 1/20 of the project per day.
- B completes the project in 30 days, so B's work rate is 1/30 of the project per day.
2. Combined Work Rate:
- When A and B work together, their combined work rate is the sum of their individual work rates.
- Therefore, A and B's combined work rate is 1/20 + 1/30 = 1/12 of the project per day.
3. Work Done by A before Quitting:
- Since A quits 10 days before the project is completed, A works for 10 days.
- In 10 days, A completes 10 * (1/20) = 1/2 of the project.
4. Remaining Work:
- After A quits, B is left to complete the remaining 1/2 of the project.
- With a combined work rate of 1/12 per day, B will take 1/2 / (1/12) = 6 days to complete the remaining work.
5. Total Time to Complete the Project:
- A worked for 10 days and B worked for 6 days after A quit, so the total time taken to complete the project is 10 + 6 = 16 days.
Therefore, the project will be completed in 16 days, which aligns with option 'A' as the correct answer.
Free Test
Community Answer
A can complete a project in 20 days and B can complete the same projec...
A can complete a project in 20 days. So, A will complete 1/20th of the project in a day.
B can complete a project in 30 days. So, B will complete 1/30th of the project in a day.
Let the total number of days taken to complete the project be 'x' days.
The value of x is the answer to the question.
B worked all x days. However, A worked for (x - 10) days because A quits 10 days before the project is completed.
In a day, A completes 1/20th of the project.
Therefore, A would have completed  of the project in (x - 10) days.
In a day, B completes 1/30th of the project.
Therefore, B would have completed x/30th of the project in x days.

3x - 30 + 2x = 60
5x = 90 or x = 18
Choice A is the correct answer.
Attention GMAT Students!
To make sure you are not studying endlessly, EduRev has designed GMAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in GMAT.
Explore Courses for GMAT exam

Similar GMAT Doubts

Top Courses for GMAT

A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer?
Question Description
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer? for GMAT 2024 is part of GMAT preparation. The Question and answers have been prepared according to the GMAT exam syllabus. Information about A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for GMAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer?.
Solutions for A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for GMAT. Download more important topics, notes, lectures and mock test series for GMAT Exam by signing up for free.
Here you can find the meaning of A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?a)18 daysb)27 daysc)26.67 daysd)16 dayse)12 daysCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice GMAT tests.
Explore Courses for GMAT exam

Top Courses for GMAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev