GMAT Exam  >  GMAT Questions  >  Six machines, each working at the same consta... Start Learning for Free
Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?
  • a)
    2
  • b)
    3
  • c)
    4
  • d)
    6
  • e)
    8
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
Six machines, each working at the same constant rate, together can com...
If each machine works at a rate of "x" days to complete the job individually, the equation representing the work rate of six machines becomes:
1/x + 1/x + 1/x + 1/x + 1/x + 1/x = 1/12
Simplifying this equation, we find:
6/x = 1/12
Solving for "x", we get:
x = 72
Now, let "y" represent the number of machines needed to complete the job in 8 days. The equation representing the work rate of all machines becomes:
y/72 = 1/8
Simplifying this equation, we find:
y = 9
To determine the additional number of machines required, we subtract the initial number of machines (6) from the required number of machines (9):
required = y - x = 3
Therefore, the answer is B. 3.
Free Test
Community Answer
Six machines, each working at the same constant rate, together can com...
Given:
- 6 machines can complete a job in 12 days
- All machines work at the same constant rate

To find:
- How many additional machines are needed to complete the job in 8 days

Let's assume that one machine completes 1 unit of work in 1 day. Therefore, the total work required to complete the job is 6 units (6 machines * 12 days).

Step 1: Find the rate of each machine
Since all machines work at the same constant rate, each machine completes 1/12th of the job in 1 day.

Step 2: Find the rate of all machines combined
Since there are 6 machines, the combined rate of all machines is 6 * 1/12 = 1/2 units per day.

Step 3: Find the work remaining after 8 days
In 8 days, the machines working at the same rate will complete 8 * 1/2 = 4 units of work (since the combined rate is 1/2 units per day).

Step 4: Find the additional machines required to complete the remaining work in 8 days
The remaining work is 6 - 4 = 2 units.
To complete the remaining work in 8 days, each additional machine needs to work at the same rate of 1/2 units per day.

Let's assume the number of additional machines required is x.
Therefore, the combined rate of all machines would be (6 + x) * 1/2 units per day.

Step 5: Set up the equation
To complete 2 units of work in 8 days, the equation becomes:
2 = 8 * (6 + x) * 1/2

Step 6: Solve for x
2 = 8 * (6 + x) * 1/2
2 = 4(6 + x)
2 = 24 + 4x
4x = 2 - 24
4x = -22
x = -22/4
x = -11/2

Since the number of machines cannot be negative, we discard the negative solution.

Therefore, the number of additional machines required to complete the job in 8 days is 3 (option B).
Attention GMAT Students!
To make sure you are not studying endlessly, EduRev has designed GMAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in GMAT.
Explore Courses for GMAT exam

Similar GMAT Doubts

Top Courses for GMAT

Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer?
Question Description
Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer? for GMAT 2024 is part of GMAT preparation. The Question and answers have been prepared according to the GMAT exam syllabus. Information about Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for GMAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer?.
Solutions for Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for GMAT. Download more important topics, notes, lectures and mock test series for GMAT Exam by signing up for free.
Here you can find the meaning of Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer?, a detailed solution for Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the Job in 8 days?a)2b)3c)4d)6e)8Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice GMAT tests.
Explore Courses for GMAT exam

Top Courses for GMAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev