A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is
  • a)
    5 MW
  • b)
    4 MW
  • c)
    6 MW
  • d)
    10 MW
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
A generating station has a maximum demand of 30 MW, a load factor of 6...
View all questions of this test
Most Upvoted Answer
A generating station has a maximum demand of 30 MW, a load factor of 6...
Given parameters:
- Maximum demand (MD) = 30 MW
- Load factor (LF) = 60%
- Plant capacity factor (PCF) = 50%

To find: Reserve capacity of the plant

Formulae:
- Plant capacity (PC) = MD / LF
- Actual energy generated (AEG) = PC x PCF
- Reserve capacity (RC) = PC - AEG

Calculation:
- PC = 30 / 0.6 = 50 MW
- AEG = 50 x 0.5 = 25 MW
- RC = 50 - 25 = 25 MW

Therefore, the reserve capacity of the plant is 6 MW (option C).
Free Test
Community Answer
A generating station has a maximum demand of 30 MW, a load factor of 6...
B
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer?
Question Description
A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer?.
Solutions for A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A generating station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant isa)5 MWb)4 MWc)6 MWd)10 MWCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev