A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work?
Most Upvoted Answer
A can do a piece of work in 20 days and B can do it in 30 days. A star...
Work Capacity of A and B
A can complete the work in 20 days, which means his work capacity is:
  • A's work rate = 1/20 work per day


B can complete the same work in 30 days, so his work capacity is:
  • B's work rate = 1/30 work per day



Work Done by A in the First 5 Days
When A works alone for the first 5 days:
  • Work done by A in 5 days = 5 * (1/20) = 5/20 = 1/4 of the work



Remaining Work After 5 Days
After A has worked for 5 days, the remaining work is:
  • Remaining work = 1 - 1/4 = 3/4 of the work



Combined Work Rate of A and B
When B joins A, their combined work rate is:
  • Combined work rate = (1/20) + (1/30)
  • To add these fractions, find a common denominator (60):
  • Combined work rate = (3/60) + (2/60) = 5/60 = 1/12 work per day



Time Taken to Complete Remaining Work
Now, to find how long it will take for A and B to finish the remaining 3/4 of the work:
  • Time = Remaining work / Combined work rate = (3/4) / (1/12)
  • Time = (3/4) * (12/1) = 36/4 = 9 days



Total Time to Complete the Work
Finally, the total number of days to complete the work is:
  • Total time = Time worked by A alone + Time worked together = 5 days + 9 days = 14 days


Thus, A and B complete the work in **14 days**.
Explore Courses for SSC CHSL exam

Top Courses for SSC CHSL

A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work?
Question Description
A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work? for SSC CHSL 2025 is part of SSC CHSL preparation. The Question and answers have been prepared according to the SSC CHSL exam syllabus. Information about A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work? covers all topics & solutions for SSC CHSL 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work?.
Solutions for A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work? in English & in Hindi are available as part of our courses for SSC CHSL. Download more important topics, notes, lectures and mock test series for SSC CHSL Exam by signing up for free.
Here you can find the meaning of A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work? defined & explained in the simplest way possible. Besides giving the explanation of A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work?, a detailed solution for A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work? has been provided alongside types of A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work? theory, EduRev gives you an ample number of questions to practice A can do a piece of work in 20 days and B can do it in 30 days. A started the work and after 5 days B joins him. What is the total number of days taken by them to complete the work? tests, examples and also practice SSC CHSL tests.
Explore Courses for SSC CHSL exam

Top Courses for SSC CHSL

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev