Class 10 Exam  >  Class 10 Questions  >  8 girls and 12 boys can finish work in 10 day... Start Learning for Free
8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.       

  • a)
    120, 130       

  • b)
    140,280       

  • c)
    240,280       

  • d)
    100,120

Correct answer is option 'B'. Can you explain this answer?
Verified Answer
8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boy...
Work done by 1 girl and 1 boy in x and y days respectively.


work done by 1 girl and 1 boy in 1 day is (1/x) and (1/y).


so, work done by 8 girls and 12 boys in 1 day is (8/x) + (12/y) = 1/10


let (1/x) = a and (1/y) = b


so, 8a + 12b = 1/10


→ 80a + 120b = 1 ---- (1)


work done by 6 girls and 8 boys in 1 day is (6/x) + (8/y) = 1/14


6a + 80 = 1/14


→ 84a + 112b = 1 ---- (2)


By elimination method, Multiple equation 1 by 21 on both sides, we get


1680a + 2520b = 21 ---- (3)


Multiply equation 2 by 20 on both sides, we get


1680a + 2240b = 20 ---- (4)


On solving equation 3 and 4, we get


2520 b - 2240b = 21 - 20


→ 280 b = 1


→ b = 1/280


b =1/y


→ 1/280 = 1/y


→ y = 280


80a + 120 x (1/280) = 1 (From 1)


→ 80a + (3/7) = 1


→ 80a = 1 - (3/7)


→ 80a = (7 - 3)/7


→ 80a = 4/7


→ a = 4/(7 × 80)


→ a = 1/140


→ a = 1/x


→ 1/140 = 1/x


→ x = 140


1 girl and 1 boy alone take 140 days and 280 days to complete a work.
View all questions of this test
Most Upvoted Answer
8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boy...
Given data:

- 8 girls and 12 boys can finish work in 10 days.
- 6 girls and 8 boys can finish it in 14 days.

Let's assume that the work requires a certain amount of effort, which we can measure in terms of "work units".

Let the total work be represented by W. Then,

- In the first case, 8 girls and 12 boys complete the work in 10 days. So, their combined rate of work is:

Rate of work of 1 girl + Rate of work of 1 boy = W / (8 x 10) + W / (12 x 10)

- In the second case, 6 girls and 8 boys complete the same work in 14 days. So, their combined rate of work is:

Rate of work of 1 girl + Rate of work of 1 boy = W / (6 x 14) + W / (8 x 14)

Since the amount of work is the same in both cases, we can equate the two expressions for the combined rate of work:

W / (8 x 10) + W / (12 x 10) = W / (6 x 14) + W / (8 x 14)

Simplifying this equation, we get:

3W / 240 + 2W / 240 = W / 168 + W / 224

Multiplying both sides by the LCM of the denominators (which is 1680), we get:

21W + 14W = 10W + 12W

25W = 22W

W = 0

This implies that the work cannot be completed at all, which is clearly not possible. Therefore, there must be an error in the data given.

However, let's assume that there is a typo in the question, and the second case should be "4 girls and 8 boys can finish it in 14 days". Then, we can proceed as follows:

- In the first case, the combined rate of work of 8 girls and 12 boys is:

Rate of work of 1 girl + Rate of work of 1 boy = W / (8 x 10) + W / (12 x 10)

Simplifying this, we get:

Rate of work of 1 girl + Rate of work of 1 boy = W / 80

- In the second case, the combined rate of work of 4 girls and 8 boys is:

Rate of work of 1 girl + Rate of work of 1 boy = W / (4 x 14) + W / (8 x 14)

Simplifying this, we get:

Rate of work of 1 girl + Rate of work of 1 boy = W / 56

Now, we can set up two equations:

- For the rate of work of girls:

8 x (Rate of work of 1 girl + Rate of work of 1 boy) = 6 x (Rate of work of 1 girl + Rate of work of 1 boy)

Simplifying this, we get:

2(Rate of work of 1 girl + Rate of work of 1 boy) = Rate of work
Free Test
Community Answer
8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boy...
Please explain this answer
Attention Class 10 Students!
To make sure you are not studying endlessly, EduRev has designed Class 10 study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Class 10.
Explore Courses for Class 10 exam

Top Courses for Class 10

8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer?
Question Description
8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer? for Class 10 2024 is part of Class 10 preparation. The Question and answers have been prepared according to the Class 10 exam syllabus. Information about 8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Class 10 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer?.
Solutions for 8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Class 10. Download more important topics, notes, lectures and mock test series for Class 10 Exam by signing up for free.
Here you can find the meaning of 8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer?, a detailed solution for 8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of 8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 8 girls and 12 boys can finish work in 10 days while 6 girls and 8 boys can finish it in 14 days. Find the time taken by the one girl alone that by one boy alone to finish the work.a)120, 130b)140,280c)240,280d)100,120Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Class 10 tests.
Explore Courses for Class 10 exam

Top Courses for Class 10

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev