Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  The normal duration and normal cost of an act... Start Learning for Free
The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will be
  • a)
    45,500 rupees
  • b)
    47,500 rupees
  • c)
    52,500 rupees
  • d)
    54,500 rupees
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
The normal duration and normal cost of an activity are 25 days and 50,...
The increase in direct cost for 3 days crashing
= 1500×3 
= 4500 rupees
The decrease in indirect cost for 2 days
= 1000×2 
= 2000 rupees
The total cost of the activities after crashing
=  50000 + 4500 - 2000
= 52500 rupees
View all questions of this test
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer?
Question Description
The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer?.
Solutions for The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The normal duration and normal cost of an activity are 25 days and 50,000 rupees respectively. The activity crash duration is 22 days and the indirect cost is 1000 rupees per day. If the cost slope is 1500 rupees per day, then the crash cost of the activity will bea)45,500 rupeesb)47,500 rupeesc)52,500 rupeesd)54,500 rupeesCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev