All Exams  >   CUET Commerce  >   General Test Preparation for CUET UG  >   All Questions

All questions of Time & Work for CUET Commerce Exam

P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in
  • a)
    30 days
  • b)
    25 days
  • c)
    20 days
  • d)
    15 days
Correct answer is option 'B'. Can you explain this answer?

Let distance between the two places = d km
Let total time taken by faster horse = t hr
⇒ Total time taken by slower horse = (t + 5) hr,
Therefore,
speed of the faster horse = d/t km/hr
speed of the slower horse = d/(t + 5) km/hr 
The two horses meet each other in 3 hour 20 min i.e. in 3(1/3) hr = 10/3 hr
In this time, total distance travelled by both the horses together is d. 
d/(t+5) * 10/3 + d/t * 10/3 = d
⇒ 10/(3(t+5)) + 10/3t = 1
⇒ 10t + 10(t+5) = 3t(t+5)
⇒ 20t + 50 = 3t+ 15t
⇒ 3t− 5t − 50 = 0
⇒ 3t+ 10t − 15t − 50 = 0
⇒ t(3t + 10) − 5(3t + 10) = 0
⇒ (3t + 10)(t − 5) = 0
t = 5 (ignoring -ve value) 
Thus, Total time taken by slower horse = 5 + 5 = 10 hr
So Option B is correct

Anup can dig a well in 10 days. but particularly in difficult time the work is such that due to fatigue every subsequent day efficiency of a worker falls by 10%.If Anup is given a task of digging one such well in the difficult time, then in how many days will he finish the work?
  • a)
    12th day
  • b)
    15 th day
  • c)
    11th day
  • d)
    Never
Correct answer is option 'D'. Can you explain this answer?

Wizius Careers answered
Correct Answer :- d
Explanation : The total no. of days in which Anoop can dig the well is 10 days.
Anoop's one day efficiency is 10%.
On day one Anoop performs 10% of his work efficiency, then the next day he won't be able to perform because as per the question the efficiency of a worker falls by 10%.
thus, 10%-10% = 0.

P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?
  • a)
    8/15
  • b)
    7/15
  • c)
    11/15
  • d)
    2/11
Correct answer is option 'A'. Can you explain this answer?

Since P to R is double the distance of P to Q,
Therefore, it is evident that the time taken from P to R and back would be double the time taken from P to Q and back (i.e. double of 6.5 hours = 13 hours).
Since going from P to R takes 9 hours, coming back from R to P would take 4 hours i.e. 139 = 4
So Option A is correct

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
  • a)
    30 days
  • b)
    40 days
  • c)
    60 days
  • d)
    70 days
Correct answer is option 'C'. Can you explain this answer?

Sameer Rane answered
Let A's 1 day's work = x and B's 1 day's work = y.

Then, x + y =1/30 and 16x + 44y = 1.

Solving these two equations, we get: x = 1/60 and y = 1/60

 B's 1 day's work = 1/60.

Hence, B alone shall finish the whole work in 60 days.

10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
  • a)
    3
  • b)
    5
  • c)
    7
  • d)
    Cannot be determined
Correct answer is option 'C'. Can you explain this answer?

Dhruv Mehra answered
1 woman's 1 day's work = 1/70
1 child's 1 day's work = 1/140
(5 women + 10 children)'s day's work = (5/70 + 10/140) = (1/14 + 1/14) = 1/7
5 women and 10 children will complete the work in 7 days.

A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn, i.e., first day A does it alone, second day B does it alone and 3rd day C does it alone. After that the cycle is repeated till the work is finished. They get Rs 240 for this job. If the wages are divided in proportion to the work each had done. Find the amount A will get?
  • a)
    14
  • b)
    24
  • c)
    34
  • d)
    36
Correct answer is 'B'. Can you explain this answer?

Ishani Rane answered
Work done by A in 1 day = 1/90
Work done by B in 1 day = 1/40
Work done by C in 1 day = 1/12
Work done in 3 days = 1/90 + 1/40 + 1/12 = 43/360
in 8 * 3 = 24 days , work completed = 8 * 43/360 = 344/360
Remaining work = 1 - 344/360 = 16/360
in 25th day, A works and completes 1/90 work .
Remaining work = 16/360 - 1/90 = 12/360
in 26th day, B works and completes 1/40 work .
Remaining work = 12/360 - 1/40 = 1/120
in 27th day, C works and completes this entire 1/120 work
A worked 9 days by doing 1/90 work each day. Total work done by A = 9 * 1/90 = 1/10
B worked 9 days by doing 1/40 work each day. Total work done by B = 9 * 1/40 = 9/40
C worked 9 days by doing 1/12 work in the initial 8 days and 1/120 work in the 9th day.
Total work done by C = 8 * 1/12 + 1/120 = 81/120
Work done by A : Work done by B : Work done by C
= 1/10 : 9/40 : 81/120 
= 12 : 27 : 81
Total amount that they get = 240
Amount that A get = 240 * 12/(12+27+81) = Rs.24

P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
  • a)
    8
  • b)
    5
  • c)
    4
  • d)
    6
Correct answer is option 'D'. Can you explain this answer?

Initial distance = 25 dog leaps
Per-minute dog makes 5 dog leaps and cat makes 6 cat leaps = 3 dog leaps
⇒  Relative speed = 2 dog leaps / minutes
⇒  An initial distance of 25 dog leaps would get covered in 12.5 minutes.
So Option D is correct

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
  • a)
    15
  • b)
    16
  • c)
    18
  • d)
    25
Correct answer is option 'B'. Can you explain this answer?

Ratio of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4.
Suppose Tanya takes x days to do the work.
5 : 4 :: 20 : x     x = (4 * 20/5)
 x = 16 days.
Hence, Tanya takes 16 days to complete the work.

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
  • a)
    8 days
  • b)
    10 days
  • c)
    12 days
  • d)
    15 days
Correct answer is option 'C'. Can you explain this answer?

Let total work be 30 units (LCM of 10 and 15).
In one day, A can do 2 units of work and B can do 3 units of work.
In one day, both A and B can do 5 units of work.
In two days, A and B will complete 10 units of work. Remaining 20 units can be completed by A in 10 days (at rate of 2 units per day).
Hence, whole work will be completed in 12 days.

In what time would a cistern be filled by three pipes of diameter of 1 cm, 2 cm and 3 cm if the largest pipe alone can fill the cistern in 49 minutes, the amount of water flowing through each pipe being proportional to the square of its diameter?
  • a)
    31.5 minutes
  • b)
    63 minutes
  • c)
    126 minutes
  • d)
    None of these
Correct answer is option 'A'. Can you explain this answer?

Naroj Boda answered
Since the amount of water flowing through each pipe is proportional to square of its diameter so if efficiency of longest pipe (3 cm) = 1/49
Then efficiency of pipe (2 cm) = 4/(49 x 9)
and efficiency of pipe (1 cm) = 1/ (49 x 9) 
Now let cistern is filled by all three pipes in x minutes.

Directions for Question: Study the following and answer the questions that follow.
A gas cylinder can discharge gas at the rate of 1 cc/minute from burner A and at the rate of 2 cc/minute from burner B (maximum rates of discharge). The capacity of the gas cylinder is 1000 cc of gas.
The amount of heat generated is equal to 1 kcal per cc of gas.
However, there is wastage of the heat as per follows:

@ (Include higher extremes)
Q. For Question 3, if burner A had been opened only 25% and burner B had been opened 50%, the amount of heat available for cooking would be
  • a)
    780 kcal
  • b)
    800 kcal
  • c)
    750 kcal
  • d)
    Cannot be determined
Correct answer is option 'A'. Can you explain this answer?

Divey Sethi answered
First, let's find the rate at which each burner discharges gas when opened at the given percentages.

For burner A, opened at 25%:
Rate of discharge = 1 cc/min * 25% = 0.25 cc/min

For burner B, opened at 50%:
Rate of discharge = 2 cc/min * 50% = 1 cc/min

Now, let's find the wastage of heat for each burner based on the given discharge rates.

For burner A, with a discharge rate of 0.25 cc/min:
Wastage = 10% (since it falls within the 0 - 0.5 cc/min range)

For burner B, with a discharge rate of 1 cc/min:
Wastage = 25% (since it falls within the 1 - 1.5 cc/min range)

Now, we can find the effective heat generated by each burner after accounting for wastage.

For burner A:
Effective heat = 1 kcal/cc * (1 - 10%) = 1 kcal/cc * 90% = 0.9 kcal/cc

For burner B:
Effective heat = 1 kcal/cc * (1 - 25%) = 1 kcal/cc * 75% = 0.75 kcal/cc

Next, we need to find the total amount of gas discharged by both burners until the gas cylinder is empty. Since the capacity of the cylinder is 1000 cc, we can find the time it takes for both burners to empty the cylinder.

Total rate of discharge = 0.25 cc/min (burner A) + 1 cc/min (burner B) = 1.25 cc/min

Time to empty the cylinder = 1000 cc / 1.25 cc/min = 800 minutes

Now, we can find the total heat generated by each burner during these 800 minutes.

Heat generated by burner A = 0.9 kcal/cc * 0.25 cc/min * 800 min = 180 kcal

Heat generated by burner B = 0.75 kcal/cc * 1 cc/min * 800 min = 600 kcal

Finally, we can find the total heat available for cooking by adding the heat generated by both burners.

Total heat available = 180 kcal (burner A) + 600 kcal (burner B) = 780 kcal

So, the amount of heat available for cooking would be 780 kcal.

A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in
  • a)
    4 days
  • b)
    6 days
  • c)
    8 days
  • d)
    18 days
Correct answer is option 'A'. Can you explain this answer?

BT Educators answered
Ratio of rates of working of A and B = 2 : 1
So, ratio of time taken = 1 : 2
B's 1 day's work = 1/12
∴ A's one day work = 1/3 (2 times of B's work)
(A + B)'s 1 day's work = (1/6) + (1/12) = 3/12 = 1/4
So, A and B together can finish work in 4 days.

Chetan is thrice as efficient as Mamta and together they can finish a piece of work in 60 days. Mamta will take how many days to finish this work alone?
  • a)
    80
  • b)
    160
  • c)
    240
  • d)
    320
Correct answer is option 'C'. Can you explain this answer?

  • Chetan is thrice as efficient as Mamta.
  • Let, Mamta takes 3x days and Chetan takes x days to complete the work.
  • ∴ 1/x + 1/3x = 1/60 ⇒ x = 80.
  • ∴ Mamta will take 80 × 3 = 240 days to complete the work.

A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:
  • a)
    1/24
  • b)
    7/24
  • c)
    24/7
  • d)
    4
Correct answer is option 'C'. Can you explain this answer?

Divey Sethi answered
A’s 1 day work = 1/24
B’s 1 day work = 1/6
C’s 1 day work = 1/12
(A+B+C)’s 1 day work = 1/24 + 1/6 + 1/12 = 7/24
The work will be completed by them is 24/7 days.

6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.
  • a)
    4 days
  • b)
    6 days
  • c)
    2 days
  • d)
    8 days
Correct answer is option 'A'. Can you explain this answer?

Let work done by 1 man in 1 day = m and work done by 1 woman in 1 day = b 
Work done by 6 men and 8 women in 1 day = 1/10 
=> 6m + 8b = 1/10
=> 60m + 80b = 1    (1)
Work done by 26 men and 48 women in 1 day = 1/2 
=> 26m + 48b =1/2
=> 52m + 96b = 1    (2)
Solving equation 1 and equation 2. We get m = 1/100 and b = 1/200
Work done by 15 men and 20 women in 1 day 
= 15/100 + 20/200 =1/4
=> Time taken by 15 men and 20 women in doing the work = 4 days

Mayank can do 50% more work than Shishu in the same time. Shishu alone can do a piece of work in 30 hours. Shishu starts working and he had already worked for 12 hours when Mayank joins him. How many hours should Shishu and Mayank work together to complete the remaining work?
  • a)
    6
  • b)
    12
  • c)
    4.8
  • d)
    7.2
Correct answer is option 'D'. Can you explain this answer?

Ishani Rane answered
Shishu alone does the work in 30 hours 

So in 1 hour he does 1/30 of the work 

Mayank in 1 hour does 1/30 + 1/2*1/30= 1/30 +1/60 = 3/60 = 1/20 of the work 

Together in 1 hour they do 1/30 +1/20 = 5/60 = 1/12 of the work 

Together they can finish the work in 12 hours 

Shishu in 12 hours does 12/ 30 = 2/5 

Remaining work = 3/5 

3/5 X 12 = 36/5 = 7.2 hours

Read the passage below and solve the questions based on it.
The tank at a water supply station is filled with water by several pumps. At first three pumps of Ihe same capacity are turned on: 2.5 hours later, two more pumps (both the same) of a different capacity are set into operation. After 1 hour, the additional pumps were set into operation; the tank was almost filled to its capacity (15 m3 were still lacking): in another hour the tank was full. One of the two additional pumps could have filled the tank in 40 hours
Q. What is the volume of the tank?
  • a)
    60 m3
  • b)
    80 m3
  • c)
    75 m3
  • d)
    90 m3
Correct answer is option 'A'. Can you explain this answer?

Bhavya Saha answered
Let us assume that, first three pumps fills the tank in x hours .
so,
→ Efficiency of each pump = (1/x) m³ / hour .
then,
→ Efficiency of three pump = (3/x) m³ / hour .
 
now,
→ First three pumps works for = 2.5h + 1h + 1h = 4.5 hours.
 
so,
→ Water filled by 3 pumps in 4.5 hours = 4.5 * (3/x) = (13.5/x) m³ .
 
now, given that,
→ Time taken by additional pump to fill the tank = 40 hours.
so,
→ Efficiency of 2 additional tanks = 2 * (1/40) = (1/20) m³ / h .
 
and,
→ Additional pumps work for = 1 + 1 = 2 hours.
 
so,
→ Water filled by additional pumps in 2 hours = 2 * (1/20) = (1/10) m³ .
 
therefore,
→ (13.5/x) + (1/10) = 1
→ (13.5/x) = 1 - (1/10)
→ (13.5/x) = (9/10)
→ x = 135/9 = 15 hours.
 
since given that, in last 1 hour they filled 15 m³ .
 
hence,
→ 3 * (1/15) + (1/20) = 15 m³
→ (1/5) + (1/20) = 15
→ (4 + 1)/20 = 15
→ (5/20) = 15
→ (1/4) = 15
→ 1 = 60  (Ans.) (Option A)

A finishes 6 / 7th of the work in 2z hours, B works twice as fast and finishes the remaining work. For how long did B work?
  • a)
  • b)
  • c)
  • d)
Correct answer is option 'D'. Can you explain this answer?

Amit Kumar answered
Since A finishes 6 / 7th of the work in 2z hours.
B would finish 12 / 7 of the work in 2z hours.
Thus, to do 1/7th of the work (which represents the remaining work), B would require
     ► 2z /12 = z / 6 hours.

If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?
  • a)
    60
  • b)
    45
  • c)
    40
  • d)
    30
Correct answer is option 'A'. Can you explain this answer?

Sagar Sharma answered
Explanation:

Given data:
- A+B can complete work in 15 days
- B alone can complete work in 20 days

Let's calculate:

Efficiency:
Let's assume the total work to be done is 60 units (LCM of 15 and 20)
- A+B's efficiency: 60/15 = 4 units/day
- B's efficiency: 60/20 = 3 units/day

Work done by A alone:
As A+B's efficiency is 4 units/day and B's efficiency is 3 units/day, A's efficiency will be the difference between the two, which is 1 unit/day.

Time taken by A alone to complete the work:
Now, as A's efficiency is 1 unit/day, A will take 60 units of work in 60 days.
Therefore, A alone can complete the work in 60 days.
So, the correct answer is option A) 60.

Refer to the data below and answer the questions that follow.
Anoop was writing the reading comprehension sections in Lhe DOG entrance examinations, There were four passages of exactly equal length in terms of number of words and die four passages had 5, 8, 8 and 6 questions following each of them respectively. It is known that Anoop can answer exactly 12 questions in the time he takes to read any one of the four passages. Assume that his rate of reading and answering questions remains the same throughout the section.
Q.
By what per cent should Anoop increase his reading speed if he has to cut down on his total time spent on the section by 20%? Assume that the time spent on answering the questions is constant and as given in the directions.
  • a)
    36.36%
  • b)
    54.54%
  • c)
    50.50%
  • d)
    45.45%
Correct answer is option 'D'. Can you explain this answer?

Maulik Rane answered
To solve this problem, let's first find out the total time Anoop takes to read all four passages and answer all the questions.

Let the time he takes to read one passage be T. Since there are four passages, he takes 4T time to read all the passages. It is given that he can answer 12 questions in the time he takes to read one passage. So, the time he takes to answer one question is T/12.

There are a total of 5+8+8+6 = 27 questions. The time he takes to answer all the questions is 27 * (T/12) = 27T/12 = 9T/4.

Now, the total time spent on the section is the sum of the time spent on reading all the passages and answering all the questions: 4T + 9T/4 = 25T/4.

To cut down on his total time spent on the section by 20%, the new total time should be 80% of the original time, which is 0.8 * (25T/4) = 5T.

Since the time spent on answering the questions remains constant, the time spent on reading should reduce to 5T - 9T/4 = 11T/4. The new time he takes to read one passage is (11T/4) / 4 = 11T/16.

Now, let's find out the percentage increase in reading speed. The original time to read one passage is T, and the new time is 11T/16. Since speed is inversely proportional to time, the new speed will be 16/11 times the original speed.

The percentage increase in speed is [(16/11 - 1) * 100] = [(5/11) * 100] = 45.45%.

So, Anoop should increase his reading speed by 45.45% to cut down on his total time spent on the section by 20%.

A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
  • a)
    Rs. 375
  • b)
    Rs. 400
  • c)
    Rs. 600
  • d)
    Rs. 800
Correct answer is 'B'. Can you explain this answer?

Sameer Rane answered
Payment is always directly proportional to efficiency, that is more the efficiency higher the payLet the total work be eating 24 chocolates (LCM of 6 and 8)Therefore in one day A can eat = 24/6 = 4B can eat = 24/8 = 3All three together in one day can = 24/3 = 8This means C can eat 1 chocolate in 1 daySo efficiency ratio of A:B:C = 4:3:1Therefore payment will also be in same ratioC gets 1/8 th of the amount = 1/8 * 3200 = 400 Rs

A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
  • a)
    15 days
  • b)
    20 days
  • c)
    25 days
  • d)
    30 days
Correct answer is option 'C'. Can you explain this answer?

Anirban Khanna answered
LCM(10,50)=50
 
Suppose total work is 50 units.

Work done by A and B together in 1 day 

= 50/10 = 5 unit.

Work done by C in 1 day

= 50/50 = 1 unit.

Work done by A,B,C together in 1 day 

= 5 + 1 = 6 unit.

Since work done by A is equal to work done by B and C together,
work done by B and C together in 1 day 

= 6/2 = 3 unit.

Work done by B in 1 day 

= 3 − 1 = 2 unit.

Therefore, B alone can do the work in 50/2 = 25 days.

4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
  • a)
    35
  • b)
    40
  • c)
    45
  • d)
    50
Correct answer is option 'B'. Can you explain this answer?

Ishani Rane answered
Let 1 man's 1 day work = x and 1 woman's 1 day work = y.
Then, 4x + 6y = 1/8 and 3x + 7y = 1/10
Solving these two equations, we get:
x = 11/400 and y = 1/400
10 woman's 1 day work = (1/400 x 10) = 1/40.
Hence, 10 women will complete the work in 40 days.

A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
  • a)
    5
  • b)
    6
  • c)
    5.5
  • d)
    8
Correct answer is option 'B'. Can you explain this answer?

Sagar Sharma answered
Solution:

Given:
A can finish the work in 18 days.
B can finish the work in 15 days.
B worked for 10 days.

Calculating the work done by B:
One day work of B = 1/15
Work done by B in 10 days = 10*(1/15) = 2/3

Calculating the work remaining:
Remaining work = 1 - 2/3 = 1/3

Calculating the work done by A in a day:
One day work of A = 1/18

Calculating the time taken by A to finish the remaining work:
Let A takes x days to finish the remaining work.
Work done by A in x days = x*(1/18)
According to the question,
Work done by A + Work done by B = Remaining work
x*(1/18) + 2/3 = 1/3
x/18 = 1/3 - 2/3
x/18 = -1/3
x = -6
Since time cannot be negative, we take the positive value.
Therefore, A alone can finish the remaining work in 6 days.
Therefore, the correct answer is option B) 6 days.

Two pipes can separately fill a tank in 20 hours and 30 hours respectively. Both the pipes are opened to fill the tank but when the tank is 3/4th full, a leak develops in, through which one-fourth of water supplied by both the pipes goes out. What is the total time taken to fill the tank?
  • a)
    18 hours
  • b)
    14 hours
  • c)
    15 hours
  • d)
    13 hours
Correct answer is option 'D'. Can you explain this answer?

Answer: Option D
Explanation :Time to completely fill the tank by the two pipe:
1/20 + 1/30= 1/n 
⇒ n = 12 hours
So, 3/4th of the tank will be filled in 3/4 × 12 = 9 hours.
Remaining time = 12 – 9 = 3 hours.
But, for the remaining 1/4th of the tank, the combined efficiency drops to 3/4th (1/4th is getting leaked), 
∴ Time required will be come 4/3 times, i.e. 4/3 × 3 = 4 hours.
Hence, total time taken to fill the tank = 9 + 4 = 13 hours.
Hence, option (d).

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
  • a)
    60/11
  • b)
    31/11
  • c)
    71/11
  • d)
    72/11
Correct answer is option 'A'. Can you explain this answer?

P can complete the work in (12 * 8) hrs = 96 hrs 
Q can complete the work in (8 * 10) hrs=80 hrs 
Therefore, P's 1 hour work=1/96   and Q's 1 hour work= 1/80
(P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs  
Therefore, Number of days of 8 hours each = (480/11) * (1/8) = 60/11

Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is
  • a)
    8
  • b)
    9
  • c)
    6
  • d)
    4
Correct answer is option 'C'. Can you explain this answer?

EduRev CLAT answered
Let the time taken by Anu, Tanu and Manu be 5x, 8x and 10x hours.
Total work = LCM(5x, 8x, 10x) = 40x
Anu can complete 8 units in one hour
Tanu can complete 5 units in one hour
Manu can complete 4 units in one hour
It is given, three of them together can complete in 32 hours.
32(8 + 5 + 4) = 40x
x = 685568​
It is given,
Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day, i.e. 36 + 4 = 40 hours
40(8 + 5) + y(4) = 40x
4y = 24
y = 6
Manu alone will complete the remaining work in 6 hours.
Option C

A man, a woman or a boy can do a job in 20 days, 30 days or 60 days respectively. How many boys must assist 4 men and 5 women to do the work in 2 days?
  • a)
    16
  • b)
    14
  • c)
    15
  • d)
    None of these
Correct answer is option 'D'. Can you explain this answer?

Given Data:
- A man can do the job in 20 days
- A woman can do the job in 30 days
- A boy can do the job in 60 days

Calculating Efficiency:
- Efficiency of a man = 1/20
- Efficiency of a woman = 1/30
- Efficiency of a boy = 1/60

Efficiency of 4 men, 5 women, and x boys working together:
- (4 * 1/20) + (5 * 1/30) + (x * 1/60) = 1/2
- Simplifying, we get: 1/5 + 1/6 + x/60 = 1/2
- LCM of 5, 6, and 60 is 60
- Multiplying throughout by 60, we get: 12 + 10 + x = 30
- Solving for x, we get: x = 8

Number of Boys required:
- Therefore, 8 boys must assist 4 men and 5 women to do the work in 2 days.
Therefore, the correct answer is option D - None of these.

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?
  • a)
    18 days
  • b)
    24 days
  • c)
    30 days
  • d)
    36 days
Correct answer is option 'A'. Can you explain this answer?

Ishani Rane answered
Let total work be 120 units  (LCM of 30, 24 and 20).

(A+B)'s one day work = 4 units

(B+C)'s one day work = 5 units

(C+A)'s one day work = 6 units

Adding all three equations and then dividing by 2,

(A+B+C)'s one day work = 7.5 units

A's one day work = 7.5 - 5 = 2.5 units

In 10 days, all three complete 75 units of work. Remaining 45 units can be completed by A in 18 days (at rate of 2.5 units per day).

The correct option is A.

Chapter doubts & questions for Time & Work - General Test Preparation for CUET UG 2025 is part of CUET Commerce exam preparation. The chapters have been prepared according to the CUET Commerce exam syllabus. The Chapter doubts & questions, notes, tests & MCQs are made for CUET Commerce 2025 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests here.

Chapter doubts & questions of Time & Work - General Test Preparation for CUET UG in English & Hindi are available as part of CUET Commerce exam. Download more important topics, notes, lectures and mock test series for CUET Commerce Exam by signing up for free.

Top Courses CUET Commerce