GATE Exam  >  GATE Questions  >  A contract is to be completed in 52 days and ... Start Learning for Free
 A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?  
  • a)
    50
  • b)
    89
  • c)
    146
  • d)
    175 
Correct answer is option 'A,B,C,D'. Can you explain this answer?
Verified Answer
A contract is to be completed in 52 days and 125 identical robots were...
Total man-hours per day = 125x7 = 875
Total man-hours in 39 days = 875x39 = 34125
Fraction of work complete = 5/7
The whole work needs = 7/5 x 34125 = 47775 man-hours
Remaining man-hours for the work to be completed = 47775-34125 = 13650
No. of days left = 52-39 = 13 days
Man-hours per day = 13650/13 = 1050
If each man works for 8hr /day, then no. of men = 1050/8 = 131.25 ≈ 132 men
No. of additional men = 132 - 125 = 7 men
7 men need to be added so as to complete the work on time.
View all questions of this test
Most Upvoted Answer
A contract is to be completed in 52 days and 125 identical robots were...
Given information:
- Contract duration: 52 days
- Number of robots: 125
- Robots' operational hours per day: 7 hours
- Work completed after 39 days: 5/7 of the total work
- New operational hours per robot: 8 hours

Calculation:
Total work to be completed = 1 (100%)
Work completed after 39 days = 5/7
Remaining work = 1 - 5/7 = 2/7

Let's calculate the number of days required to complete the remaining work using the concept of man-days:

Total man-days required = Total work / Work done per day

Total work = Remaining work = 2/7
Work done per day = Number of robots * Operational hours per robot

For the initial 39 days, the robots were operational for 7 hours a day. So, the total work done per day = 125 * 7
For the remaining days, the robots will be operational for 8 hours a day. So, the total work done per day = (125 + X) * 8

Equating the total man-days required for both cases:

(2/7) / ((125 * 7) / 39) = (2/7) / ((125 + X) * 8) / (52 - 39)

Simplifying the equation:

39 * (125 * 7) = (52 - 39) * (125 + X) * 8
39 * 875 = 13 * (125 + X) * 8
(125 + X) * 8 = (39 * 875) / 13
125 + X = (39 * 875) / (13 * 8)
X = ((39 * 875) / (13 * 8)) - 125

Calculating the value of X:

X = (27375 / 104) - 125
X = 263.9423077 - 125
X ≈ 138.94

Therefore, approximately 139 additional robots would be required to complete the work on time.

Answer: Option A (139)
Explore Courses for GATE exam

Similar GATE Doubts

A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer?
Question Description
A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer?.
Solutions for A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer?, a detailed solution for A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer? has been provided alongside types of A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?a)50b)89c)146d)175Correct answer is option 'A,B,C,D'. Can you explain this answer? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev