Quant Exam  >  Quant Questions  >  Manoj takes twice as much time as Anjay and t... Start Learning for Free
Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?
  • a)
    6 days
  • b)
    3 days
  • c)
    2 days
  • d)
    4 days
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Manoj takes twice as much time as Anjay and thrice as much as Vijay to...
Let Anjay take 3t days, Vijay take 2t days and Manoj take 6t days in order to complete the work.
Then we get:
1/3t + 1/2t + 1/6t = 1 Æ t = 1. Thus, Manoj would take 6t = 6 days to complete the work.
View all questions of this test
Most Upvoted Answer
Manoj takes twice as much time as Anjay and thrice as much as Vijay to...
Given information:
- Manoj takes twice as much time as Anjay to finish a piece of work.
- Manoj takes thrice as much time as Vijay to finish a piece of work.
- Together they finish the work in 1 day.

To find:
- The time taken by Manoj to finish the work.

Solution:
Let's assume that Vijay takes 'x' days to finish the work.
- Therefore, Anjay would take '2x' days to finish the work, as Manoj takes twice as much time as Anjay.
- And, Manoj would take '3x' days to finish the work, as Manoj takes thrice as much time as Vijay.

Now, let's calculate the combined work done by all three of them in a day:
- Vijay does 1/x of the work in a day.
- Anjay does 1/(2x) of the work in a day, as he takes twice as much time as Vijay.
- Manoj does 1/(3x) of the work in a day, as he takes thrice as much time as Vijay.
- So, the combined work done by all three of them in a day would be: 1/x + 1/(2x) + 1/(3x) = (6 + 3 + 2)/6x = 11/6x

As per the question, they finish the work in 1 day. Therefore, the combined work done by all three of them in a day would be equal to 1. Hence, we can write:

11/6x = 1
x = 11/6

- So, Vijay takes 11/6 days to finish the work.
- Anjay takes twice the time, i.e. 22/6 = 11/3 days to finish the work.
- Manoj takes thrice the time, i.e. 33/6 = 11/2 days to finish the work.

Therefore, the time taken by Manoj to finish the work is 11/2 days, which is option A.
Explore Courses for Quant exam
Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer?
Question Description
Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer?.
Solutions for Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Manoj takes twice as much time as Anjay and thrice as much as Vijay to finish a piece of work.Together they finish the work in 1 day. What is the time taken by Manoj to finish the work?a)6 daysb)3 daysc)2 daysd)4 daysCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev