Banking Exams Exam  >  Banking Exams Questions  >  Efficiency of B is two times more than effici... Start Learning for Free
Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work? 
  • a)
    24 days 
  • b)
    30 days 
  • c)
    36 days 
  • d)
    48 days 
  • e)
    18 days 
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Efficiency of B is two times more than efficiency of A. Both started w...
Lets efficiency of A is x unit/day and B's efficiency is 3x unit/day
So, B work for 19 days and A work for 18 days
ATQ—
Total work = 19 × 3x + 18 × x = 75x
Efficency of C 
+ 1.5x units/ day
View all questions of this test
Most Upvoted Answer
Efficiency of B is two times more than efficiency of A. Both started w...
Given: Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. C alone completes the same work in 50 days.

Let's assume the efficiency of A = x, then the efficiency of B = 2x (as given in the question).

Efficiency of A = x
Efficiency of B = 2x

As they work alternatively, starting with B, the total number of days taken to complete the work = 37.

Let's assume A worked for 'y' days, then B worked for '2y' days (as B's efficiency is twice that of A).

Total number of days = y + 2y = 3y

So, 3y = 37

Therefore, y = 37/3

Now, we can find the total work done by A and B in a day.

Work done by A in a day = 1/x
Work done by B in a day = 1/2x

Total work done in a day by A and B = 1/x + 1/2x = 3/2x

As they completed the work in 37 days, the total work done in a day by A and B = 1/37

So, we have 3/2x = 1/37

Solving the above equation, we get x = 74.

Therefore, Efficiency of A = 74 and Efficiency of B = 148.

Now, we need to find in how many days A and C together will complete the work.

Efficiency of A and C together = 1/74 + 1/50 = 12/925

So, A and C together can complete the work in 925/12 days.

Simplifying, we get 77.08 days, which is approximately equal to 30 days (approx).

Hence, the correct answer is option (b) 30 days.
Free Test
Community Answer
Efficiency of B is two times more than efficiency of A. Both started w...
Answer ( B ) 30 days
Explore Courses for Banking Exams exam

Similar Banking Exams Doubts

Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer?
Question Description
Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer? for Banking Exams 2024 is part of Banking Exams preparation. The Question and answers have been prepared according to the Banking Exams exam syllabus. Information about Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Banking Exams 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams. Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone complete the same work in 50 days then find in how many days A and C together will complete the work?a)24 daysb)30 daysc)36 daysd)48 dayse)18 daysCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Banking Exams tests.
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev