Quant Exam  >  Quant Questions  >  9 men and 12 women can complete the job in 12... Start Learning for Free
9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?
  • a)
    36days
  • b)
    42days
  • c)
    30days
  • d)
    28days
  • e)
    None of these
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
9 men and 12 women can complete the job in 12 days.In how many days ca...
9m+12w = 1/12
3m+4w = ?
3(3m+4w) = 1/12
3m+4w = 1/36
View all questions of this test
Most Upvoted Answer
9 men and 12 women can complete the job in 12 days.In how many days ca...
Given information:
- 9 men and 12 women can complete the job in 12 days.

We need to find:
- In how many days can 3 men and 4 women finish the same job working together?

Let's assume that the work done by one man in one day is "m" units, and the work done by one woman in one day is "w" units.

Calculation:
- We are given that 9 men and 12 women can complete the job in 12 days.
- So, the total work done by them in one day is (9m + 12w).
- We can write the equation as: (9m + 12w) * 12 = 1 (as they complete the job in 12 days).

Now, we need to find the number of days required for 3 men and 4 women to finish the same job working together.
- Let's assume this number of days as "d".
- So, the total work done by 3 men and 4 women in one day is (3m + 4w).
- We can write the equation as: (3m + 4w) * d = 1.

To find the value of "d", we can equate the two equations:
(9m + 12w) * 12 = (3m + 4w) * d

Simplifying the equation:
108m + 144w = 3md + 4wd
108m + 144w = (3m + 4w) * d

We know that the left-hand side of the equation represents the work done by 9 men and 12 women in 12 days, which is equal to 1.
So, we can write this as: 108m + 144w = 1.

Substituting this value in the equation:
1 = (3m + 4w) * d

Simplifying further:
1 = 3md + 4wd

Comparing the coefficients of "m" and "w" on both sides of the equation:
3d = 108 => d = 36

Hence, 3 men and 4 women can finish the same job working together in 36 days. Therefore, the correct answer is option A, 36 days.
Explore Courses for Quant exam

Similar Quant Doubts

9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?
Question Description
9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about 9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for 9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?.
Solutions for 9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of 9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of 9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for 9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of 9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice 9 men and 12 women can complete the job in 12 days.In how many days can 3 men and 4 women finish the same job working together ?a)36daysb)42daysc)30daysd)28dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev