Quant Exam  >  Quant Questions  >  A certain number of men take 45 days to compl... Start Learning for Free
A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.
  • a)
    30
  • b)
    40
  • c)
    50
  • d)
    60
  • e)
    None of these
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A certain number of men take 45 days to complete a work. If there are ...
Let initially there are X men. Then x*45 = (x-10)*60. So we get x = 40
View all questions of this test
Most Upvoted Answer
A certain number of men take 45 days to complete a work. If there are ...
Given:
Let the original number of men be x.
They take 45 days to complete the work.
If there are 10 men less, then they will take 60 days to complete the work.

Approach:
We can solve this problem using the concept of work done. The total work done is the same in both cases, so we can equate the work done by the two groups of men.

Solution:

Step 1: Determine the work done by the group of men who take 45 days to complete the work.
Let the work done be W.
We know that work done is equal to the product of the number of men, the number of days, and the efficiency of each man.
Efficiency is the reciprocal of the time taken by one man to complete the work.
So, the efficiency of each man is 1/45.

Therefore, the work done by the group of men who take 45 days to complete the work is:
W = x * 45 * (1/45) = x

Step 2: Determine the work done by the group of men who take 60 days to complete the work.
If there are 10 men less, the new number of men will be (x - 10).
The efficiency of each man in this case is 1/60.

Therefore, the work done by the group of men who take 60 days to complete the work is:
W = (x - 10) * 60 * (1/60) = (x - 10)

Step 3: Equate the work done by the two groups of men.
Since the total work done is the same, we have:
x = (x - 10)

Step 4: Solve the equation to find the value of x.
x - x + 10 = 0
10 = 0

Therefore, the original number of men is 10.

Step 5: Check the options.
None of the given options match the solution obtained above.

Conclusion:
The given options do not match the solution obtained. Therefore, the original number of men cannot be determined from the given information.
Free Test
Community Answer
A certain number of men take 45 days to complete a work. If there are ...
Let initially there are X men. Then x*45 = (x-10)*60. So we get x = 40
Explore Courses for Quant exam
A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer?
Question Description
A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A certain number of men take 45 days to complete a work. If there are 10 men less then they will take 60 days to complete the work. Find the original number of men.a)30b)40c)50d)60e)None of theseCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev