Quant Exam  >  Quant Questions  >  A contractor undertakes to do a job in 18 day... Start Learning for Free
A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?
  • a)
    20
  • b)
    25
  • c)
    30
  • d)
    40
  • e)
    None of these
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
A contractor undertakes to do a job in 18 days. He employees certain n...
Answer – c) 30 Explanation : Let ‘m’ men are originally employed m*18 = (m -12)*30 m = 30
View all questions of this test
Most Upvoted Answer
A contractor undertakes to do a job in 18 days. He employees certain n...
Easy one-
let total work= total man days =LCM(18,30)=90 man days or 90 work.
so to accomplish 90 works 5 men to be done for 18 days = 18*5=90 works
and to complete 90 works in 30 days,3 men to be done in a day.

so difference in men is 2 ,but as per qn 12 men were less. and 12 is 6 times 2.so multiply 6 with everything in the entire equation.but we need total men for 18 days .so 5 men * 6= 30 men , which is actual expected men and so the answer.and actually present men were 30-12=18.

ANS IS 30 MEN.
Free Test
Community Answer
A contractor undertakes to do a job in 18 days. He employees certain n...
Given:
- A contractor undertakes to do a job in 18 days.
- He employs a certain number of men, but 12 of them being absent from the very first day.
- The rest can complete the work in 30 days.

To find: The number of men originally employed.

Solution:
Let's assume that the total work to be done is 1 unit (for simplicity).

Let's say the number of men originally employed is x.

Work done by x men in 1 day = 1/18 (since they can complete the work in 18 days)

Work done by 1 man in 1 day = (1/18)/x = 1/18x

Let's say the number of men who were present from the first day is y (out of x men).

So the work done by y men in 1 day = y/18x

Since the remaining men (x-y) can complete the work in 30 days,

Work done by x-y men in 1 day = 1/(30(x-y))

Total work done by all men in a day = y/18x + 1/(30(x-y))

We know that if all x men were present, they could have completed the work in 18 days. So,

Work done by x men in 1 day = 1/18

Work done by 1 man in 1 day = 1/18x (as derived earlier)

Total work done by all x men in a day = x/18x = 1/18

We can equate the above two equations to get:

y/18x + 1/(30(x-y)) = 1/18

Simplifying the equation, we get:

y/2x + 1/(5(x-y)) = 1/3

Multiplying both sides by 30x(x-y), we get:

15y(x-y) + 6x(x-y) = 10x^2

Simplifying further, we get:

10x^2 - 21xy + 6y^2 = 0

We need to find the value of x.

We know that x > y (since 12 men were absent from the first day)

We can factorize the above equation as:

(10x - 3y)(x - 2y) = 0

Since x > y, we can ignore the second factor and consider only the first factor:

10x - 3y = 0

10x = 3y

y = (10/3)x

Since y is an integer, x should be a multiple of 3 and a factor of 10.

The possible values of x are: 3, 6, 10, 15, 30, 5, 20, 25, 40, 50

Out of these, the only value that satisfies the equation y = (10/3)x is x = 30.

Therefore, the number of men originally employed is 30.

Answer: (c) 30.
Explore Courses for Quant exam

Similar Quant Doubts

To maximize profits, an employer should control his or her environment in a factory, shop, or office and make sure that examples of energy and efficiency are numerous enough to catch employee attention and establish an atmosphere of industry. In the workplace, there are instances in which it would be in the mutual interest of the employer and the employees to increase the speed of work, but conditions may limit or forbid the use of pace-setters. In construction work and in some of the industries, where there are minute subdivisions of operations and continuity of processes, this method of increasing efficiency is very commonly applied with the use of time cards and software. In many factories, however, such an effort to speed up production might stir resentment, even among the workers paid at a fixed rate for each unit produced or action performed, and have an effect exactly opposite to that desired. The alternative, of course, is for the employer to secure unconscious pace setting by providing incentives for the naturally ambitious men and women in the way of a premium or bonus system or other reward for above-average efficiency.Accordingly, to take advantage of the benefits of conscious or voluntary imitation, workers must be provided with examples that appeal to them as admirable and inspire the wish to emulate them. A common application of this principle is seen in the choice of department heads, foremen, and other bosses. Invariably these people win promotion by industry, skill, and efficiency greater than that displayed by their direct peers, or by mastery of their skills that enables them to show their less efficient peers how any and all operations should be conducted. This focusing of attention upon individuals worthy of imitation has been carried much farther by various companies. Some create weekly or monthly papers published primarily for circulation within the organization to record every incident reflecting unusual skill, initiative, or personal power in an individual member of the organization. A big order closed, a difficult contract secured, a complex or delicate operation performed in less than the usual time, a new personal record in production, the invention of an unproved method or machinewhatever the achievement, it is described and glorified, its perpetrator praised and held up for emulation. This, indeed, is one of the methods by which the larger sales organizations have obtained remarkable results.The author of the passage mentions a big order closed, a difficult contract secured, a complex or delicate operation performed in less than the usual time, etc., in order to

A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer?
Question Description
A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer?.
Solutions for A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev