Question Description
A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared
according to
the Quant exam syllabus. Information about A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer?.
Solutions for A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant.
Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A contractor undertakes to do a job in 18 days. He employees certain number of men, but 12 of them being absent from the very first day, the rest can complete the work in 30 days. The number of men originally employed?a)20b)25c)30d)40e)None of theseCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Quant tests.