Quant Exam  >  Quant Questions  >  A contractor undertakes to make a mall in 60 ... Start Learning for Free
A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?
  • a)
    20men
  • b)
    25men
  • c)
    30men
  • d)
    40men
  • e)
    None of these
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
A contractor undertakes to make a mall in 60 days and he employs 30 me...
Let total work is w and it is given that one-third of the work is completed after 30 days. Means
M*D = 30*30 = w/3, so total work = 30*30*3
2700 = 30*30 + (30+p)*30, so we get P = 30 (p = additional men)
View all questions of this test
Most Upvoted Answer
A contractor undertakes to make a mall in 60 days and he employs 30 me...
Given:
- Time required to complete the mall = 60 days
- Number of men employed initially = 30
- Work completed in the first 30 days = 1/3

To complete the remaining 2/3 of the work in the remaining 30 days, the contractor would need to increase the workforce. Let's assume that the number of extra men required is x.

Workforce required to complete the remaining 2/3 of the work:
- In the first 30 days, 1/3 of the work is completed by 30 men
- So, the remaining 2/3 of the work would require the same 30 men and additional x men
- Total workforce required = 30 + x

Now, we can use the concept of work done to find the value of x.

Work done = (Number of men) x (Time taken)
As the work to be done is the same, we can equate the left-hand side of the equation for the first 30 days and the remaining 30 days.

Work done in the first 30 days = Work done in the remaining 30 days
(30 men) x (30 days) x (1/3) = (30 + x men) x (30 days) x (2/3)

Solving this equation, we get:
x = 30 men

Therefore, the contractor would need to employ an additional 30 men to complete the work on time. Hence, the correct answer is option C.
Explore Courses for Quant exam

Similar Quant Doubts

To maximize profits, an employer should control his or her environment in a factory, shop, or office and make sure that examples of energy and efficiency are numerous enough to catch employee attention and establish an atmosphere of industry. In the workplace, there are instances in which it would be in the mutual interest of the employer and the employees to increase the speed of work, but conditions may limit or forbid the use of pace-setters. In construction work and in some of the industries, where there are minute subdivisions of operations and continuity of processes, this method of increasing efficiency is very commonly applied with the use of time cards and software. In many factories, however, such an effort to speed up production might stir resentment, even among the workers paid at a fixed rate for each unit produced or action performed, and have an effect exactly opposite to that desired. The alternative, of course, is for the employer to secure unconscious pace setting by providing incentives for the naturally ambitious men and women in the way of a premium or bonus system or other reward for above-average efficiency.Accordingly, to take advantage of the benefits of conscious or voluntary imitation, workers must be provided with examples that appeal to them as admirable and inspire the wish to emulate them. A common application of this principle is seen in the choice of department heads, foremen, and other bosses. Invariably these people win promotion by industry, skill, and efficiency greater than that displayed by their direct peers, or by mastery of their skills that enables them to show their less efficient peers how any and all operations should be conducted. This focusing of attention upon individuals worthy of imitation has been carried much farther by various companies. Some create weekly or monthly papers published primarily for circulation within the organization to record every incident reflecting unusual skill, initiative, or personal power in an individual member of the organization. A big order closed, a difficult contract secured, a complex or delicate operation performed in less than the usual time, a new personal record in production, the invention of an unproved method or machinewhatever the achievement, it is described and glorified, its perpetrator praised and held up for emulation. This, indeed, is one of the methods by which the larger sales organizations have obtained remarkable results.The author of the passage mentions a big order closed, a difficult contract secured, a complex or delicate operation performed in less than the usual time, etc., in order to

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer?
Question Description
A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer?.
Solutions for A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extra men should he employ so that the work is completed on time?a)20menb)25menc)30mend)40mene)None of theseCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev