Quant Exam  >  Quant Questions  >  A piece of work is to be completed in 100days... Start Learning for Free
A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?
  • a)
    5
  • b)
    6
  • c)
    7
  • d)
    11
  • e)
    None
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
A piece of work is to be completed in 100days, 11 Men are employed to ...
11*50/1/3 = (11+x)*50/2/3
X = 11
View all questions of this test
Most Upvoted Answer
A piece of work is to be completed in 100days, 11 Men are employed to ...
Given:
Total days = 100
Number of men employed initially = 11
Work completed in 50 days = 1/3

Let's calculate the work done by 11 men in 50 days:
Work done by 11 men in 50 days = 1/3
Work done by 1 man in 50 days = (1/3)/11 = 1/33

Let's calculate the work done by 11 men in 1 day:
Work done by 1 man in 1 day = 1/33
Work done by 11 men in 1 day = 11/33 = 1/3

Let's calculate the work left to be done:
Work left to be done = 1 - 1/3 = 2/3

Let's calculate the total work to be done:
Total work = 1

Let's calculate the number of days left to complete the work:
Days left to complete the work = 100 - 50 = 50

Let's calculate the work done by the 11 men in 50 days:
Work done by 11 men in 50 days = (1/3)

Let's calculate the work done by the 11 men in 1 day:
Work done by 11 men in 1 day = (1/3)/50 = 1/150

Let's calculate the work done by 1 man in 1 day:
Work done by 1 man in 1 day = (1/150)/11 = 1/1650

Let's calculate the number of men required to complete the work in 50 days:
Total work to be done = 2/3
Work done by 1 man in 1 day = 1/1650
Work done by n men in 1 day = (1/1650)*n
(1/1650)*n*50 = 2/3
n = (2/3)*(1650/50)
n = 44

Therefore, the additional number of men required to work to finish the work in time is 44 - 11 = 33. However, since the question is asking for the total number of men required, the answer would be 11 + 33 = 44, which is not an option. Therefore, the correct answer is option D, which is 11.
Free Test
Community Answer
A piece of work is to be completed in 100days, 11 Men are employed to ...
11*50/1/3 = (11+x)*50/2/3
X = 11
Explore Courses for Quant exam
A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer?
Question Description
A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer?.
Solutions for A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A piece of work is to be completed in 100days, 11 Men are employed to do the work it is found that after 50 days only 1/3 rd work is completed. Now additionally how many more Men are to be employed to work to finish the work in time?a)5b)6c)7d)11e)NoneCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev