Question Description
P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?a)100/9 daysb)100/11 daysc)100/7 daysd)100/13 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared
according to
the Quant exam syllabus. Information about P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?a)100/9 daysb)100/11 daysc)100/7 daysd)100/13 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?a)100/9 daysb)100/11 daysc)100/7 daysd)100/13 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?.
Solutions for P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?a)100/9 daysb)100/11 daysc)100/7 daysd)100/13 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant.
Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?a)100/9 daysb)100/11 daysc)100/7 daysd)100/13 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?a)100/9 daysb)100/11 daysc)100/7 daysd)100/13 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?a)100/9 daysb)100/11 daysc)100/7 daysd)100/13 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?a)100/9 daysb)100/11 daysc)100/7 daysd)100/13 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice P, Q and R can do a piece of work in 16, 24 and 30 days respectively. They started the work simultaneously but P stops the work after 4 days and Q called off the work 2 days before the completion. In what time the work is finished?a)100/9 daysb)100/11 daysc)100/7 daysd)100/13 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Quant tests.