Quant Exam  >  Quant Questions  >  Mahesh and Umesh can complete a work in 10 da... Start Learning for Free
Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed in
  • a)
    7 days
  • b)
    9 days
  • c)
    11 days
  • d)
    12 days
  • e)
    None of these
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
Mahesh and Umesh can complete a work in 10 days and 15 days respective...
Umesh 5 days work =5/15;
remaining work =1-1/3=2/3;
together 1 day work of Mahesh and Umesh = 1/15+1/10= 1/6;
so, they will do together 2/3 of work in =(2/3)/+(1/6) =4 days.
hence, the work was completed in (4+5) =9 days. op(b)
Free Test
Community Answer
Mahesh and Umesh can complete a work in 10 days and 15 days respective...
Given data:
Mahesh can complete work in 10 days
Umesh can complete work in 15 days

Let's assume the total work to be done is "x"
So, the work done by Umesh in one day = x/15
And the work done by Mahesh in one day = x/10

Umesh starts the work and works for 5 days, so the work done by Umesh in 5 days = 5(x/15) = x/3
Now, the remaining work = x - x/3 = 2x/3

Now, both Umesh and Mahesh work together on remaining work = 2x/3
Let's assume that they take 'n' days to complete the remaining work together.
So, the work done by Umesh in 'n' days = n(x/15)
And the work done by Mahesh in 'n' days = n(x/10)

Total work done in 'n' days = n(x/15) + n(x/10) = (2nx/30) + (3nx/30) = 5nx/30 = nx/6

According to the question, the total number of days taken to complete the work together is 9 days.
So, the work done by Umesh in 5 days + the work done by both Umesh and Mahesh in 9 days = x
x/3 + nx/6 = x
n/2 + 1 = 2
n/2 = 1
n = 2

So, the remaining work will be completed by both Umesh and Mahesh in 2 days.
Therefore, the total number of days taken to complete the work = 5 (days taken by Umesh) + 2 (days taken by both Umesh and Mahesh) = 7 days.

Hence, the correct answer is option B) 7 days.
Explore Courses for Quant exam
Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer?
Question Description
Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? for Quant 2025 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Quant 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Mahesh and Umesh can complete a work in 10 days and 15 days respectively. Umesh starts the work and after 5 days Mahesh also joins him. In all, the work would be completed ina)7 daysb)9 daysc)11 daysd)12 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev