GATE Exam  >  GATE Questions  >  A project has three activities A followed by ... Start Learning for Free
A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?
Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 units
Activity B : 5 weeks-200 units, 4 weeks-225 units
Activity C : 3 weeks-700 units, 2 weeks-800 units
  • a)
    1650
  • b)
    1725
  • c)
    1800
  • d)
    1850
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
A project has three activities A followed by B which is followed by C....
Activities having the least crash slope are crashed first.
Indirect cost for 15 weeks = 25 × 15 = 375.
Total cost = 1425 + 375 = 1800
View all questions of this test
Explore Courses for GATE exam
A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer?
Question Description
A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer?.
Solutions for A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer?, a detailed solution for A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A project has three activities A followed by B which is followed by C. Taking indirect cost of 25 units per week, the cost of completing the project in 15 weeks is given by?Activity A : 10 weeks-400 units, 9 weeks-450 units, 8 weeks-500 unitsActivity B : 5 weeks-200 units, 4 weeks-225 unitsActivity C : 3 weeks-700 units, 2 weeks-800 unitsa)1650b)1725c)1800d)1850Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev