A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs
800Q, where Q is the daily production in tonnes. What is the cost of production in Rs per
tonne for a daily production of 100 tonnes?
    Correct answer is '1300'. Can you explain this answer?
    Verified Answer
    A foundry has a fixed daily cost of Rs 50,000 whenever it operates and...
    View all questions of this test
    Explore Courses for GATE exam
    A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer?
    Question Description
    A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer?.
    Solutions for A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
    Here you can find the meaning of A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer?, a detailed solution for A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer? has been provided alongside types of A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A foundry has a fixed daily cost of Rs 50,000 whenever it operates and a variable cost of Rs800Q, where Q is the daily production in tonnes. What is the cost of production in Rs pertonne for a daily production of 100 tonnes?Correct answer is '1300'. Can you explain this answer? tests, examples and also practice GATE tests.