SSC Exam  >  SSC Questions  >   Three men and eight machines can finish a jo... Start Learning for Free
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?
Correct answer is '13'. Can you explain this answer?
Verified Answer
Three men and eight machines can finish a job in half the time taken ...
Consider the work done by a man in a day = a and that by a machine = b
Since, three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job, hence the efficiency will be double.
=> 3a+8b = 2(3b+8a)
=>13a=2b
Hence work done by 13 men in a day = work done by 2 machines in a day.
=> If two machines can finish the job in 13 days, then same work will be done 13 men in 13 days.
Hence the required number of men = 13
View all questions of this test
Most Upvoted Answer
Three men and eight machines can finish a job in half the time taken ...
Given information:
- Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job.
- Two machines can finish the job in 13 days.

To find:
- How many men can finish the job in 13 days?

Assumptions:
- The amount of work done by each machine or man is constant.

Solution:

Let's assume:
- The amount of work done by one machine in one day is "M" units.
- The amount of work done by one man in one day is "N" units.

Step 1: Calculate the work done by two machines in 13 days:
- Two machines can finish the job in 13 days.
- So, the work done by two machines in 13 days = 2 x 13M = 26M units.

Step 2: Calculate the work done by three men and eight machines in a certain time:
- Let's assume the time taken by three men and eight machines to finish the job is "T" days.
- The work done by three men and eight machines in "T" days = (3N x T) + (8M x T) = (3N + 8M)T units.

Step 3: Calculate the work done by three machines and eight men in the same time:
- The work done by three machines and eight men in "T" days = (3M x T) + (8N x T) = (3M + 8N)T units.

Step 4: Use the given information to form an equation:
- According to the given information, the work done by three men and eight machines in "T" days is half the work done by three machines and eight men in the same time.
- (3N + 8M)T = 0.5 x (3M + 8N)T
- 3N + 8M = 0.5 x (3M + 8N)

Step 5: Use the given information to form another equation:
- According to the given information, the work done by two machines in 13 days is equal to the work done by three machines and eight men in a certain time.
- 2 x 13M = (3M + 8N)T
- 26M = (3M + 8N)T

Step 6: Solve the two equations:
We have two equations:
1) 3N + 8M = 0.5 x (3M + 8N)
2) 26M = (3M + 8N)T

By solving these equations, we get:
- N = 4M
- T = 13

Therefore, the number of men required to finish the job in 13 days is 13.
Explore Courses for SSC exam
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer?
Question Description
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared according to the SSC exam syllabus. Information about Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? covers all topics & solutions for SSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer?.
Solutions for Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC. Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer?, a detailed solution for Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? has been provided alongside types of Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? tests, examples and also practice SSC tests.
Explore Courses for SSC exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev