Question Description
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared
according to
the SSC exam syllabus. Information about Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? covers all topics & solutions for SSC 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer?.
Solutions for Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC.
Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer?, a detailed solution for Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? has been provided alongside types of Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?Correct answer is '13'. Can you explain this answer? tests, examples and also practice SSC tests.