For completion of a project, the critical path of a network represents-
  • a)
    Maximum time
  • b)
    Minimum time
  • c)
    Maximum cost
  • d)
    Minimum cost
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
For completion of a project, the critical path of a network represent...
In project management, a critical path is the sequence of project network activities that add up to the longest overall duration, regardless if that longest duration has float or not. This determines the shortest time possible to complete the project.
View all questions of this test
Most Upvoted Answer
For completion of a project, the critical path of a network represent...
The Critical Path Method (CPM)
The Critical Path Method (CPM) is a project management technique used to identify the longest sequence of dependent activities in a project. It helps in determining the minimum time required to complete a project by identifying the critical path. The critical path represents the series of activities that must be completed in order to finish the project within the minimum possible time.

Understanding the Critical Path
The critical path consists of activities that have zero slack or float time, which means they cannot be delayed without delaying the project. Any delay in the critical path activities will directly impact the project completion time.

Maximum Time
The critical path represents the maximum time required to complete a project. It is the longest path through the network diagram and includes activities with the longest durations. The activities on the critical path are typically marked with double lines or arrows to emphasize their importance.

Identifying the Critical Path
To determine the critical path, you need to create a network diagram that shows all the activities required to complete the project. Each activity is represented by a node, and the arrows connecting the nodes represent the dependencies between the activities. The duration of each activity is also specified.

Calculating the Critical Path
To calculate the critical path, you need to perform a forward and backward pass analysis. During the forward pass, you start with the first activity and calculate the earliest start time and earliest finish time for each subsequent activity. During the backward pass, you start with the last activity and calculate the latest start time and latest finish time for each preceding activity.

Benefits of Identifying the Critical Path
- Helps in resource allocation: By identifying the critical path, project managers can allocate resources more effectively to ensure that the activities on the critical path are completed on time.
- Allows for better scheduling: The critical path provides a clear roadmap for the project, allowing project managers to set realistic deadlines and milestones.
- Enables effective risk management: By focusing on the critical path activities, project managers can prioritize their efforts and allocate resources to manage potential risks that may impact the project timeline.

In conclusion, the critical path of a network represents the maximum time required to complete a project. It is the longest sequence of dependent activities that must be completed in order to finish the project within the minimum possible time.
Explore Courses for SSC exam
For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer?
Question Description
For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared according to the SSC exam syllabus. Information about For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for SSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer?.
Solutions for For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC. Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice For completion of a project, the critical path of a network represents-a)Maximum timeb)Minimum timec)Maximum costd)Minimum costCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice SSC tests.
Explore Courses for SSC exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev