Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts?
Most Upvoted Answer
Weekly production requirement of aproduct are 1000 units tje cycle tim...
Production Requirement for a Product

The weekly production requirement for a product is 1000 units.


Cycle Time for Producing a Product

The cycle time of producing one product on a machine is 10 minutes.


Factory Shifts

The factory works on 2 shifts, which means that there are two work shifts in a day. Each work shift is 8 hours long.


Calculating Production

To calculate the production requirements for the week, we need to use the following formula:

Production per week = (Production per day) x (Number of working days)

Production per day = (Number of hours in a day) / (Cycle time in minutes) x (Number of machines)


Calculating Production per Day

Production per day = (16 hours) / (10 minutes) x (1 machine) = 96 units


Calculating Production per Week

Production per week = (96 units) x (5 days) x (2 shifts) = 960 units


Conclusion

The factory needs to produce 960 units per week to meet the production requirement of 1000 units. This can be achieved by running two shifts per day, with one machine running continuously throughout the shift.
Community Answer
Weekly production requirement of aproduct are 1000 units tje cycle tim...
3
Explore Courses for GATE exam
Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts?
Question Description
Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts?.
Solutions for Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts? defined & explained in the simplest way possible. Besides giving the explanation of Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts?, a detailed solution for Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts? has been provided alongside types of Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts? theory, EduRev gives you an ample number of questions to practice Weekly production requirement of aproduct are 1000 units tje cycle time of producing one product on a machine is 10 min. The factory works ona 2 shifts? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev