Question Description
For a given PERT activity, the standard deviation of the time needed to complete an activity is 3. If the optimistic time and the most likely time required to complete this activity are 8 and 12 minutes respectively. Find out the expected time in order to complete this activity.a)19.32 minutesb)13.67 minutesc)18.27 minutesd)13.01 minutesCorrect answer is option 'B'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared
according to
the GATE exam syllabus. Information about For a given PERT activity, the standard deviation of the time needed to complete an activity is 3. If the optimistic time and the most likely time required to complete this activity are 8 and 12 minutes respectively. Find out the expected time in order to complete this activity.a)19.32 minutesb)13.67 minutesc)18.27 minutesd)13.01 minutesCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for For a given PERT activity, the standard deviation of the time needed to complete an activity is 3. If the optimistic time and the most likely time required to complete this activity are 8 and 12 minutes respectively. Find out the expected time in order to complete this activity.a)19.32 minutesb)13.67 minutesc)18.27 minutesd)13.01 minutesCorrect answer is option 'B'. Can you explain this answer?.
Solutions for For a given PERT activity, the standard deviation of the time needed to complete an activity is 3. If the optimistic time and the most likely time required to complete this activity are 8 and 12 minutes respectively. Find out the expected time in order to complete this activity.a)19.32 minutesb)13.67 minutesc)18.27 minutesd)13.01 minutesCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE.
Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of For a given PERT activity, the standard deviation of the time needed to complete an activity is 3. If the optimistic time and the most likely time required to complete this activity are 8 and 12 minutes respectively. Find out the expected time in order to complete this activity.a)19.32 minutesb)13.67 minutesc)18.27 minutesd)13.01 minutesCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
For a given PERT activity, the standard deviation of the time needed to complete an activity is 3. If the optimistic time and the most likely time required to complete this activity are 8 and 12 minutes respectively. Find out the expected time in order to complete this activity.a)19.32 minutesb)13.67 minutesc)18.27 minutesd)13.01 minutesCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for For a given PERT activity, the standard deviation of the time needed to complete an activity is 3. If the optimistic time and the most likely time required to complete this activity are 8 and 12 minutes respectively. Find out the expected time in order to complete this activity.a)19.32 minutesb)13.67 minutesc)18.27 minutesd)13.01 minutesCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of For a given PERT activity, the standard deviation of the time needed to complete an activity is 3. If the optimistic time and the most likely time required to complete this activity are 8 and 12 minutes respectively. Find out the expected time in order to complete this activity.a)19.32 minutesb)13.67 minutesc)18.27 minutesd)13.01 minutesCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice For a given PERT activity, the standard deviation of the time needed to complete an activity is 3. If the optimistic time and the most likely time required to complete this activity are 8 and 12 minutes respectively. Find out the expected time in order to complete this activity.a)19.32 minutesb)13.67 minutesc)18.27 minutesd)13.01 minutesCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice GATE tests.