Consider the following data:
Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?
  • a)
    29 units and 25 units
  • b)
    30 units and 25 units
  • c)
    21 units and 24 units
  • d)
    31 units and 26 units
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Consider the following data:Suppose round-robin scheduling is applied ...
Here, TQ = 2 units
Also, every scheduling OT context switch will take the overhead of 1ns. (Assume & represent overhead)
The Gant Chart will look like
Hence, completion time = 30 units
& twin around time = completion time – Arrival time
= 30 – 5
= 25 units
View all questions of this test
Most Upvoted Answer
Consider the following data:Suppose round-robin scheduling is applied ...
Here, TQ = 2 units
Also, every scheduling OT context switch will take the overhead of 1ns. (Assume & represent overhead)
The Gant Chart will look like
Hence, completion time = 30 units
& twin around time = completion time – Arrival time
= 30 – 5
= 25 units
Explore Courses for GATE exam

Similar GATE Doubts

Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer?
Question Description
Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following data:Suppose round-robin scheduling is applied to the given data with time quantum=2 units. It is also given that scheduling of a process or context switch will take 1 unit of time. What are the completion time and turnaround time of process P4?a)29 units and 25 unitsb)30 units and 25 unitsc)21 units and 24 unitsd)31 units and 26 unitsCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev