GATE Exam  >  GATE Questions  >  Workability of concrete can be measured using... Start Learning for Free
Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:
(i) As the slump increases, the Vebe time increases
(ii) As the slump increases, the compaction factor increases
Which of the following is TRUE?
  • a)
    Both (i) and (ii) are True
  • b)
    Both (i) and (ii) are False
  • c)
    (i) is True and (ii) is False
  • d)
    (i) is False and (ii) is True
Correct answer is option 'D'. Can you explain this answer?
Explore Courses for GATE exam
Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer?
Question Description
Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer?.
Solutions for Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Workability of concrete can be measured using slump, compaction factor and Vebe time. Consider the following statements for workability of concrete:(i) As the slump increases, the Vebe time increases(ii) As the slump increases, the compaction factor increasesWhich of the following is TRUE?a)Both (i) and (ii) are Trueb)Both (i) and (ii) are Falsec)(i) is True and (ii) is Falsed)(i) is False and (ii) is TrueCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice GATE tests.