Question Description
P and Q can together do a work in 6 days. If P can do the work alone in 18 days, then P is:a)As efficient as Qb)Half as efficient as Qc)Twice as efficient as Qd)Thrice as efficient as QCorrect answer is option 'B'. Can you explain this answer? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared
according to
the SSC exam syllabus. Information about P and Q can together do a work in 6 days. If P can do the work alone in 18 days, then P is:a)As efficient as Qb)Half as efficient as Qc)Twice as efficient as Qd)Thrice as efficient as QCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for SSC 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for P and Q can together do a work in 6 days. If P can do the work alone in 18 days, then P is:a)As efficient as Qb)Half as efficient as Qc)Twice as efficient as Qd)Thrice as efficient as QCorrect answer is option 'B'. Can you explain this answer?.
Solutions for P and Q can together do a work in 6 days. If P can do the work alone in 18 days, then P is:a)As efficient as Qb)Half as efficient as Qc)Twice as efficient as Qd)Thrice as efficient as QCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC.
Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of P and Q can together do a work in 6 days. If P can do the work alone in 18 days, then P is:a)As efficient as Qb)Half as efficient as Qc)Twice as efficient as Qd)Thrice as efficient as QCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
P and Q can together do a work in 6 days. If P can do the work alone in 18 days, then P is:a)As efficient as Qb)Half as efficient as Qc)Twice as efficient as Qd)Thrice as efficient as QCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for P and Q can together do a work in 6 days. If P can do the work alone in 18 days, then P is:a)As efficient as Qb)Half as efficient as Qc)Twice as efficient as Qd)Thrice as efficient as QCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of P and Q can together do a work in 6 days. If P can do the work alone in 18 days, then P is:a)As efficient as Qb)Half as efficient as Qc)Twice as efficient as Qd)Thrice as efficient as QCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice P and Q can together do a work in 6 days. If P can do the work alone in 18 days, then P is:a)As efficient as Qb)Half as efficient as Qc)Twice as efficient as Qd)Thrice as efficient as QCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice SSC tests.