Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred?  
  • a)
    EPC contract  
  • b)
    Percentage rate contract  
  • c)
    Item rate contract  
  • d)
    Lump sum contract 
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
Given that the scope of the construction work is well-defined with all...
Introduction:
When the scope of the construction work is well-defined with all its drawings, specifications, quantities, and estimates, choosing the most suitable contract type becomes crucial. The preferred contract should provide clarity, reduce risk, and ensure that the project is completed within the defined scope and budget.

Explanation:
Among the given options, the most preferred contract type in this scenario is the Lump sum contract (option D). This can be justified by considering the following factors:

1. Fixed Price:
- A lump sum contract is a fixed price contract where the contractor agrees to complete the project for a specific sum of money.
- With a well-defined scope, drawings, specifications, and quantities, a lump sum contract allows the project owner to accurately determine the total cost of the project upfront.
- This provides financial stability and predictability, as the contractor is responsible for any cost overruns or additional expenses that may arise during the construction process.

2. Clarity and Simplicity:
- A lump sum contract provides a clear and straightforward agreement between the project owner and the contractor.
- The scope of work, deliverables, and timelines are clearly defined in the contract, minimizing the potential for disputes or misunderstandings.
- This simplicity makes it easier for both parties to manage and monitor the progress of the project.

3. Risk Allocation:
- With a lump sum contract, the risk is primarily borne by the contractor.
- The contractor is responsible for completing the project within the agreed-upon budget, regardless of any cost fluctuations or unforeseen circumstances.
- This allows the project owner to transfer a significant portion of the risk to the contractor, providing a higher level of financial security.

4. Cost Control:
- A lump sum contract promotes cost control and cost certainty.
- Since the scope of work and quantities are well-defined, the contractor is incentivized to carefully plan and manage the project to avoid any cost overruns.
- This ensures that the project is completed within the allocated budget, providing financial benefits to the project owner.

Conclusion:
Considering the well-defined scope of work, drawings, specifications, quantities, and estimates, a lump sum contract is the most preferred contract type. It offers fixed pricing, clarity, simplicity, effective risk allocation, and cost control. However, it is essential to carefully draft and negotiate the contract terms to ensure that all project requirements are adequately addressed.
Explore Courses for GATE exam

Similar GATE Doubts

Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer?
Question Description
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer?.
Solutions for Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred? a)EPC contract b)Percentage rate contract c)Item rate contract d)Lump sum contractCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev