A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity is
  • a)
    100 MW
  • b)
    75 MW
  • c)
    0 MW
  • d)
    133.33 MW
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
A station operates with a load factor and plant capacity factor of 0.7...
Free Test
Community Answer
A station operates with a load factor and plant capacity factor of 0.7...
Load Factor:
The load factor is defined as the ratio of the average load over a given period of time to the maximum demand during that period. In this case, the load factor is given as 0.75.

Plant Capacity Factor:
The plant capacity factor is defined as the ratio of the actual energy generated by the plant to the maximum possible energy that could have been generated during a given period of time. In this case, the plant capacity factor is also given as 0.75.

Maximum Demand:
The maximum demand is the highest amount of power that is required by the consumers at any given time. In this case, the maximum demand is given as 100 MW.

Reserve Capacity:
The reserve capacity is the additional capacity available in the power system to meet any sudden increase in demand or to account for any unforeseen circumstances. It is usually expressed as a percentage of the maximum demand.

Calculation:
To calculate the reserve capacity, we can use the following formula:

Reserve Capacity = Maximum Demand - (Load Factor * Plant Capacity Factor * Maximum Demand)

Substituting the given values into the formula:

Reserve Capacity = 100 MW - (0.75 * 0.75 * 100 MW)
Reserve Capacity = 100 MW - (0.5625 * 100 MW)
Reserve Capacity = 100 MW - 56.25 MW
Reserve Capacity = 43.75 MW

Therefore, the reserve capacity is 43.75 MW.

Answer:
The correct answer is option 'C', 0 MW.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer?
Question Description
A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer?.
Solutions for A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A station operates with a load factor and plant capacity factor of 0.75, with a maximum demand of 100 MW. The reserve capacity isa)100 MWb)75 MWc)0 MWd)133.33 MWCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev