In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given  
by  Q=6.715 X 10-4 S0.5 n-1
 where, Q = discharge,m3 s-1, S = drain bed slope and n = Manning’s roughness coefficient. Size of the drain in mm is ________ 
    Correct answer is between '99,101'. Can you explain this answer?
    Most Upvoted Answer
    In a subsurface drainage system, the peak discharge through tile drain...
    Roughness coefficient.

    The Manning roughness coefficient (n) is a measure of the resistance to flow in the drain. It depends on the characteristics of the drain material, such as roughness and shape. The higher the value of n, the rougher the drain and the higher the resistance to flow.

    The drain bed slope (S) is the slope or gradient of the drain bed. It is usually expressed as a percentage or a ratio. A steeper slope will result in a higher discharge capacity, while a flatter slope will result in a lower discharge capacity.

    To calculate the peak discharge through the tile drain under full flow condition, you need to know the values of S and n. Once you have these values, you can substitute them into the equation Q = 6.715 X 10-4S0.5n-1 to calculate the peak discharge.

    For example, if the drain bed slope is 0.01 (1%) and the Manning roughness coefficient is 0.02, the calculation would be:

    Q = 6.715 X 10-4(0.01)0.5(0.02)-1
    Q = 6.715 X 10-4(0.01)0.5(50)
    Q = 6.715 X 10-4(0.1)(50)
    Q = 6.715 X 10-4(5)
    Q = 3.3575 X 10-3 m3s-1

    So, the peak discharge through the tile drain under full flow condition would be 3.3575 X 10-3 m3s-1.
    Explore Courses for GATE exam

    Similar GATE Doubts

    In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer?
    Question Description
    In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer?.
    Solutions for In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
    Here you can find the meaning of In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer?, a detailed solution for In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer? has been provided alongside types of In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In a subsurface drainage system, the peak discharge through tile drain under full flow condition is given by Q=6.715 X 10-4S0.5n-1where, Q = discharge,m3s-1, S = drain bed slope and n = Manning’s roughness coefficient.Size of the drain in mm is ________Correct answer is between '99,101'. Can you explain this answer? tests, examples and also practice GATE tests.
    Explore Courses for GATE exam
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev