Question Description
A can do a work in 8 days, B can do a work in 7 days, C can do a work in 6 days. A works on the first day, B works on the second day and C on the third day rely. that is they work on alternate days. When will they finish the work.(which day will they finish the work) (7+7/168)Correct answer is '8'. Can you explain this answer? for Quant 2025 is part of Quant preparation. The Question and answers have been prepared
according to
the Quant exam syllabus. Information about A can do a work in 8 days, B can do a work in 7 days, C can do a work in 6 days. A works on the first day, B works on the second day and C on the third day rely. that is they work on alternate days. When will they finish the work.(which day will they finish the work) (7+7/168)Correct answer is '8'. Can you explain this answer? covers all topics & solutions for Quant 2025 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A can do a work in 8 days, B can do a work in 7 days, C can do a work in 6 days. A works on the first day, B works on the second day and C on the third day rely. that is they work on alternate days. When will they finish the work.(which day will they finish the work) (7+7/168)Correct answer is '8'. Can you explain this answer?.
Solutions for A can do a work in 8 days, B can do a work in 7 days, C can do a work in 6 days. A works on the first day, B works on the second day and C on the third day rely. that is they work on alternate days. When will they finish the work.(which day will they finish the work) (7+7/168)Correct answer is '8'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant.
Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A can do a work in 8 days, B can do a work in 7 days, C can do a work in 6 days. A works on the first day, B works on the second day and C on the third day rely. that is they work on alternate days. When will they finish the work.(which day will they finish the work) (7+7/168)Correct answer is '8'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A can do a work in 8 days, B can do a work in 7 days, C can do a work in 6 days. A works on the first day, B works on the second day and C on the third day rely. that is they work on alternate days. When will they finish the work.(which day will they finish the work) (7+7/168)Correct answer is '8'. Can you explain this answer?, a detailed solution for A can do a work in 8 days, B can do a work in 7 days, C can do a work in 6 days. A works on the first day, B works on the second day and C on the third day rely. that is they work on alternate days. When will they finish the work.(which day will they finish the work) (7+7/168)Correct answer is '8'. Can you explain this answer? has been provided alongside types of A can do a work in 8 days, B can do a work in 7 days, C can do a work in 6 days. A works on the first day, B works on the second day and C on the third day rely. that is they work on alternate days. When will they finish the work.(which day will they finish the work) (7+7/168)Correct answer is '8'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A can do a work in 8 days, B can do a work in 7 days, C can do a work in 6 days. A works on the first day, B works on the second day and C on the third day rely. that is they work on alternate days. When will they finish the work.(which day will they finish the work) (7+7/168)Correct answer is '8'. Can you explain this answer? tests, examples and also practice Quant tests.