Quant Exam  >  Quant Questions  >  A can do a piece of work in 20 days. He works... Start Learning for Free
A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?
  • a)
    8 days
  • b)
    10 days
  • c)
    12 days
  • d)
    6 days
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
A can do a piece of work in 20 days. He works at it for 5 days and the...
Work done by A in 5 days = 1/20*5
=1/4
remaining work=(1-1/4)
=3/4
now,3/4 work is done by B in 10 days
whole work will be done by B in 10*4/3= 40/3 days
as 1 day's work of A = 1/20 
1 day's work of B =3/40
(A+B)'s 1 day's work= 1/20+3/40
= 1/8
so,both finished the work in 8 day's.
View all questions of this test
Most Upvoted Answer
A can do a piece of work in 20 days. He works at it for 5 days and the...
Given:
A can do a piece of work in 20 days.
A works for 5 days
B finishes it in 10 more days.

To find:
In how many days will A and B together finish the work?

Solution:
Let's assume the total work is 20 units (LCM of 20 and 10).

Work done by A in 5 days = (5/20) * 20 = 5 units

Remaining work = 20 - 5 = 15 units

B completes the remaining work in 10 days, so B's one day work = (15/10) = 1.5 units

Now, let's assume A's one day work = x units.

So, A can complete the total work in 20 days, hence A's one day work = (20/20) = 1 unit/day

Total work done by A and B in one day = A's one day work + B's one day work

x + 1.5 = (20/20) = 1

x = 1 - 1.5 = -0.5 (This is not possible as work done can't be negative)

So, A and B working together cannot complete the work in less than 10 days.

Now, let's assume A and B together complete the work in 'n' days.

Work done by A in 'n' days = (n/20) * 20 = n units

Work done by B in 'n' days = (n/10) * 1.5 = 1.5n units

Total work done by A and B in 'n' days = n + 1.5n = 2.5n units

As per the given condition, the total work done by A and B together = 20 units

So, 2.5n = 20

n = 8

Therefore, A and B together will finish the work in 8 days. Hence, option A is the correct answer.
Free Test
Community Answer
A can do a piece of work in 20 days. He works at it for 5 days and the...
A=20day
A do work for 5 day and remaining work is 15 and B finish this remaining work in 10 days their efficiency is
A*15=B*10
A/B=2/3
total work= efficiency*time from A
total work=2*20=40
both complete in 40/(2+3)
8 days
Explore Courses for Quant exam
A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer?
Question Description
A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer? for Quant 2025 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Quant 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer?.
Solutions for A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 moredays. In how many days will A and B together finish the work?a)8 daysb)10 daysc)12 daysd)6 daysCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev