Statement for Linked Answer Questions 64 and 65:
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
Q. The critical path for the project is
  • a)
    a – b – e – g – h
  • b)
    a – c – g – h
  • c)
    a – d – f – h
  • d)
    a – b – c – f – h
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
Statement for Linked Answer Questions 64 and 65:For a particular proje...
Critical path means "which path takes the least time "
I think A-C-G-H path takes. only takes 17 days. it will be the right answer.
Explore Courses for GATE exam
Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer?
Question Description
Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Statement for Linked Answer Questions 64 and 65:For a particular project, eight activities are to be carried out. Their relationships with other activities andexpected durations are mentioned in the table below.Q.The critical path for the project isa)a – b – e – g – hb)a – c – g – hc)a – d – f – hd)a – b – c – f – hCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev