Which one of the following is NOT a decision taken during the aggregat...
Aggregate production planning:
It is planning in which the general level of employment and output is plant to balance supply and demand for a period of fewer than 18 months
It is immediately range capacity planning, used to establish employment levels,for output rates, inventory level, subcontracting and backorders for products that are aggregated.
It is not specifically focus on the individual product but deals with product in aggregate.
View all questions of this test
Which one of the following is NOT a decision taken during the aggregat...
Aggregate Production Planning
Aggregate production planning is a strategic planning process that determines the overall production quantities and resource requirements over a specified time horizon. It involves making decisions related to production rates, workforce levels, inventory levels, and other important factors to meet the demand forecast while optimizing costs and resources.
Decision taken during Aggregate Production Planning
1. Amount of labor to be committed: This decision involves determining the number of workers required to meet the production demand. It considers factors such as available workforce, labor productivity, overtime requirements, and hiring or training needs.
2. Rate at which production should happen: This decision involves determining the production rate or output level for each period of the planning horizon. It takes into account the demand forecast, production capacity, efficiency, and other factors that influence the production rate.
3. Inventory to be carried forward: This decision involves determining the desired level of inventory to be carried forward from one period to another. It considers factors such as demand variability, lead time, storage costs, and customer service levels.
4. Scheduling of machines: This decision involves determining the production schedule for each machine or equipment. It considers factors such as machine capacity, setup time, maintenance requirements, and other constraints to ensure efficient utilization of resources.
Explanation
The correct answer is option 'A' - Scheduling of machines. Scheduling of machines is not a decision taken during the aggregate production planning stage. It falls under the detailed scheduling and execution phase, which comes after the aggregate production planning stage.
During the aggregate production planning stage, the focus is on making high-level decisions related to production rates, workforce levels, and inventory levels. These decisions are made based on the demand forecast and the organization's strategic objectives.
Once the aggregate production plan is finalized, it serves as a basis for developing the detailed production schedule, which includes the scheduling of machines, assigning specific tasks to machines, and determining the sequence of operations.
In summary, while scheduling of machines is an important aspect of production planning, it is not a decision taken during the aggregate production planning stage. The aggregate production planning stage primarily focuses on decisions related to labor commitment, production rates, and inventory levels.