SSC Exam  >  SSC Questions  >  A alone can complete work in 20 days and B al... Start Learning for Free
A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2nd day?
  • a)
    26/3 days
  • b)
    30/13 days
  • c)
    32/3 days
  • d)
    13/15 days
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
A alone can complete work in 20 days and B alone can complete work in ...
Given,
⇒ A’s 1 day’s work = 1/20
⇒ B’s 1 day’s work = 1/30
⇒ C’s 1 day’s work = 1/60
(A + B)’s 1 day’s work = 1/20 + 1/30
= 1/12
(B + C)’s 1 day’s work = 1/30 + 1/60
= 1/20
(A + B + C)’s 1 day’s work
= 1/20 + 1/30 + 1/60
= 1/10
Then,
Total work done till end of 2nd day
= 1/12 + 1/20
= 2/15
Remaining fraction of work
= 1 - 2/15
= 13/15
Total time taken by A, B and C together to complete work
= (13/15) × 10
= 26/3
It will take 26/3 days to complete remaining work.
View all questions of this test
Most Upvoted Answer
A alone can complete work in 20 days and B alone can complete work in ...
Understanding Work Rates
To solve the problem, we first need to determine the work rates of A, B, and C.
- A's work rate: A can complete the work in 20 days.
- Work rate of A = 1/20 of the work per day.
- B's work rate: B can complete the work in 30 days.
- Work rate of B = 1/30 of the work per day.
- C's work rate: C can complete the work in 60 days.
- Work rate of C = 1/60 of the work per day.

Work Done in the First Two Days
Now, we will calculate the amount of work done on the first two days.
- **Day 1 (A and B working together)**:
- Work done = (1/20 + 1/30) = (3/60 + 2/60) = 5/60 = 1/12 of the work.
- **Day 2 (B and C working together)**:
- Work done = (1/30 + 1/60) = (2/60 + 1/60) = 3/60 = 1/20 of the work.

Total Work Done in 2 Days
Now, we sum the work done over the two days:
- Total work done in 2 days = 1/12 + 1/20
To add these fractions:
- LCM of 12 and 20 = 60
- Convert to a common denominator:
- 1/12 = 5/60
- 1/20 = 3/60
- Total = (5/60 + 3/60) = 8/60 = 2/15 of the work.

Remaining Work
Total work is 1, so remaining work after 2 days is:
- Remaining Work = 1 - 2/15 = 13/15 of the work.

Work Rate of A, B, and C Together
Now, we calculate the combined work rate of A, B, and C:
- A + B + C = (1/20 + 1/30 + 1/60)
- LCM of 20, 30, and 60 = 60
- Work rate = (3/60 + 2/60 + 1/60) = 6/60 = 1/10 of the work per day.

Time to Complete Remaining Work
Finally, to find the time required to finish the remaining 13/15 of the work:
- Time = Remaining Work / Work Rate = (13/15) / (1/10) = (13/15) * (10/1) = 130/15 = 26/3 days.
Thus, the time required for A, B, and C together to complete the work after the 2nd day is **26/3 days**.
**Correct answer: Option A.**
Explore Courses for SSC exam
A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer?
Question Description
A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared according to the SSC exam syllabus. Information about A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for SSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer?.
Solutions for A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC. Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A alone can complete work in 20 days and B alone can complete work in 30 days, C alone can complete work in 60 days. If A and B work for first day and B and C work for second day then how much time it will take for A, B and C together to complete the work after 2ndday?a)26/3 daysb)30/13 daysc)32/3 daysd)13/15 daysCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice SSC tests.
Explore Courses for SSC exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev