Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?
  • a)
    24 days
  • b)
    32 days
  • c)
    34 days
  • d)
    36 days
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
Raman takes twice time as much as Ajay to do a work. If they work toge...
Let the number of days in which Ajay finishes the work be ‘d’ days.
Raman takes twice time, thus number of days in which Raman finishes the work = 2d days.
In 1 day, Ajay finishes 1/d part of the work while Ajay finishes 1/2d part of the work
Working together, in one day, they finish part of work = 1/d + 1/2d = 3/2d
∴ Number of days in which they finish the work = 2d/3
Given, they take 12 days to finish the work.
∴ 2d/3 = 12
⇒ d = 18 days
∴ Number of days Raman will take = 2d = 36 days
View all questions of this test
Explore Courses for SSC exam
Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer?
Question Description
Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared according to the SSC exam syllabus. Information about Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for SSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer?.
Solutions for Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC. Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Raman takes twice time as much as Ajay to do a work. If they work together, the work is completed in 12 days. How many days will Raman take to complete the work alone?a)24 daysb)32 daysc)34 daysd)36 daysCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice SSC tests.
Explore Courses for SSC exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev