Quant Exam  >  Quant Questions  >  P can do a piece of work in 20 days. Q is 25 ... Start Learning for Free
P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?
  • a)
    41/9
  • b)
    40/9
  • c)
    39/9
  • d)
    43/9
  • e)
    None of these
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
P can do a piece of work in 20 days. Q is 25 percent more efficient th...
Q is 25 percent more efficient so he will complete the work in 16 days
(1/20 + 1/16)*t = 1/2
View all questions of this test
Most Upvoted Answer
P can do a piece of work in 20 days. Q is 25 percent more efficient th...
Given:
P can do a piece of work in 20 days.
Q is 25% more efficient than P.

To find:
In how many days half the work is completed when both are working simultaneously.

Solution:
Let the total work to be done be 100 units.
So, P can do 5 units of work in a day.
Q is 25% more efficient than P, so Q can do 25/100 * 5 = 1.25 units of work in a day.
Therefore, both P and Q working together can do 5 + 1.25 = 6.25 units of work in a day.

Let the number of days taken to complete half the work be x.
So, in x days, P and Q working together will complete 6.25x units of work.
According to the question, 6.25x = 50
Hence, x = 50/6.25 = 8

Therefore, the answer is 8 days.

Shortcut:
Alternatively, we can use the formula:

Number of days = Total work / Work done per day

For half the work to be completed, the total work to be done is 100/2 = 50 units.
P can do 5 units of work in a day, and Q can do 1.25 units of work in a day.
So, the work done per day by both P and Q working together is 5 + 1.25 = 6.25 units.
Therefore, the number of days taken to complete half the work is 50/6.25 = 8 days.

Hence, the answer is option B) 40/9.
Free Test
Community Answer
P can do a piece of work in 20 days. Q is 25 percent more efficient th...
According to me , correct answer is option (E)
Explore Courses for Quant exam
P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer?
Question Description
P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer?.
Solutions for P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice P can do a piece of work in 20 days. Q is 25 percent more efficient than P. In how many days half the work is completed when both are working simultaneously?a)41/9b)40/9c)39/9d)43/9e)None of theseCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev