GATE Exam  >  GATE Questions  >  Terms used in engineering economics have stan... Start Learning for Free
Terms used in engineering economics have standard definitions and interpretations. Which one
of the following statements is INCORRECT?
  • a)
    The profitability measure ‘return on investment’ does not consider the time value of money
  • b)
    A cost index is an index value for a given time showing the cost at that time relative to a
    certain base time
  • c)
    The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost of
    similar equipment with a different capacity
  • d)
    The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost of
    similar equipment with a different capacity
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
Terms used in engineering economics have standard definitions and inte...
Payback period is calculated based on the payback time to cover up the fixed capital investment
only. So, statement (D) is false.
View all questions of this test
Most Upvoted Answer
Terms used in engineering economics have standard definitions and inte...
Of a project is the Net Present Value (NPV).
b)The discount rate is the rate used to calculate the present value of future cash flows.
c)The payback period is the time it takes for a project to recover its initial investment.
d)The internal rate of return (IRR) is the discount rate that makes the NPV of a project zero.
Explore Courses for GATE exam
Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer?
Question Description
Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer?.
Solutions for Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Terms used in engineering economics have standard definitions and interpretations. Which oneof the following statements is INCORRECT?a)The profitability measure ‘return on investment’ does not consider the time value of moneyb)A cost index is an index value for a given time showing the cost at that time relative to acertain base timec)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityd)The ‘six-tenths factor rule’ is used to estimate the cost of an equipment from the cost ofsimilar equipment with a different capacityCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev