A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).

A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).
    Correct answer is '1.5'. Can you explain this answer?
    Verified Answer
    A point P on a CNC controlled XY -stage is moved to another point &lsq...
    N = 800 rpm, P = 0.5 mm/rev
    V = N × P = rev/min × mm/rev = 400 mm/min

    There are two stepper motor so both will work till 0.75 min then y axis motor will stop then only x axis motor will run for 0.75 more, so total time will be 1.5 min.
    View all questions of this test
    Explore Courses for GATE exam
    A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer?
    Question Description
    A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer?.
    Solutions for A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
    Here you can find the meaning of A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer?, a detailed solution for A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer? has been provided alongside types of A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A point P on a CNC controlled XY -stage is moved to another point ‘Q’ using the coordinate system shown in the figure below and rapid positioning command (G00).A pair of stepping motors with maximum speed of 800 rpm, controlling both the X and Y motion of the stage, are directly coupled to a pair of lead screw, each with a uniform pitch of 0.5 mm. The time needed to position the point ‘P’ to the point ‘Q’ is _______ minutes. (round off to 2 decimal places).Correct answer is '1.5'. Can you explain this answer? tests, examples and also practice GATE tests.
    Explore Courses for GATE exam
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev