In PERT analysis, the time estimates of activities follow-
  • a)
    normal distribution curve
  • b)
    (β) -distribution curve
  • c)
    Poisson's distribution curve
  • d)
    binomial distribution curve
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
In PERT analysis, the time estimates of activities follow-a)normal di...
In PERT high stresses analysis, the time estimates of each activity follow (β) -distribution.
View all questions of this test
Most Upvoted Answer
In PERT analysis, the time estimates of activities follow-a)normal di...
Pert Analysis and Time Estimates

In PERT (Program Evaluation and Review Technique) analysis, the time estimates of activities are represented by probability distributions. These distributions are used to model the uncertainty and variability in the time it takes to complete each activity in a project. The most commonly used distribution in PERT analysis is the Beta distribution, which is represented by the Greek letter β.

Beta Distribution

The Beta distribution is a continuous probability distribution defined on the interval [0, 1]. It is commonly used in PERT analysis to represent activity durations because it allows for a wide range of possible values and can account for both optimistic and pessimistic estimates. The Beta distribution has two shape parameters, α (alpha) and β (beta), which determine the shape of the distribution curve.

Shape of the Beta Distribution Curve

The shape of the Beta distribution curve can vary depending on the values of the shape parameters α and β. When both α and β are equal to 1, the Beta distribution reduces to a uniform distribution, where all values between 0 and 1 are equally likely. As the values of α and β increase, the distribution becomes more peaked and concentrated around the mean.

Interpretation in PERT Analysis

In PERT analysis, the time estimates for each activity are usually provided in the form of three values: optimistic (a), most likely (m), and pessimistic (b). These values are used to calculate the shape parameters α and β of the Beta distribution.

The most likely estimate (m) is used as the mode of the distribution, while the optimistic estimate (a) and pessimistic estimate (b) are used to calculate the standard deviation of the distribution. The mean of the distribution is calculated using the formula:

mean = (a + 4m + b) / 6

The shape parameters α and β can then be calculated using the formulas:

α = ((mean - a) / (b - a)) * ((mean - a) / (b - a)) * ((mean - a) / (b - a))

β = ((b - mean) / (b - a)) * ((b - mean) / (b - a)) * ((b - mean) / (b - a))

Conclusion

In PERT analysis, the time estimates of activities follow a Beta distribution curve. This distribution allows for a range of possible values and can model the uncertainty and variability in activity durations. The shape of the Beta distribution curve is determined by the shape parameters α and β, which are calculated using the optimistic, most likely, and pessimistic estimates provided for each activity.
Explore Courses for SSC exam
In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer?
Question Description
In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared according to the SSC exam syllabus. Information about In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for SSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer?.
Solutions for In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC. Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In PERT analysis, the time estimates of activities follow-a)normal distribution curveb)(β) -distribution curvec)Poisson's distribution curved)binomial distribution curveCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice SSC tests.
Explore Courses for SSC exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev