Pick up the incorrect statement:
  • a)
    CPM is an activity-oriented network
  • b)
    PERT is event-oriented
  • c)
    Slack for any even may be positive, zero, or negative
  • d)
    Float is always negative
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Pick up the incorrect statement:a)CPM is an activity-oriented network...
Float is the range within which the start or the finish time of activity may fluctuate without affecting project completion time. Floats cannot be negative.
Hence the correct answer is option A.
View all questions of this test
Most Upvoted Answer
Pick up the incorrect statement:a)CPM is an activity-oriented network...
Explanation:
CPM stands for Critical Path Method, which is a project management technique used to analyze and schedule the activities involved in a project. The incorrect statement in this case is option 'A', which states that CPM is an activity-oriented network. However, in reality, CPM is actually an event-oriented network.

Activity-Oriented Network:
In an activity-oriented network, the focus is primarily on the activities or tasks that need to be completed in a project. The activities are represented as arrows or lines in the network diagram, and the nodes represent the events or milestones associated with the completion of those activities. The network diagram in an activity-oriented network shows the sequence of activities and their logical relationships.

Event-Oriented Network:
On the other hand, in an event-oriented network, the focus is on the events or milestones rather than the activities. The events are represented as nodes or circles in the network diagram, and the activities are represented as arrows connecting the events. The network diagram in an event-oriented network shows the sequence of events and the activities associated with each event.

Correct Statement:
Therefore, the correct statement is that CPM is an event-oriented network, not an activity-oriented network. In CPM, the network diagram is event-oriented, where the events represent the start and completion of activities, and the activities are connected to these events. The network diagram in CPM helps in determining the critical path, which is the longest path of activities that determines the minimum duration of the project.

Conclusion:
In conclusion, the incorrect statement is option 'A' which states that CPM is an activity-oriented network. The correct statement is that CPM is an event-oriented network, where the events represent the start and completion of activities.
Explore Courses for SSC exam

Similar SSC Doubts

Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer?
Question Description
Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared according to the SSC exam syllabus. Information about Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for SSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer?.
Solutions for Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC. Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Pick up the incorrect statement:a)CPM is an activity-oriented networkb)PERT is event-orientedc)Slack for any even may be positive, zero, or negatived)Float is always negativeCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice SSC tests.
Explore Courses for SSC exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev