Question Description
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,a)25 and 1b)1 and 1c)0 and 0d)81 and 0Correct answer is option 'C'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared
according to
the GATE exam syllabus. Information about A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,a)25 and 1b)1 and 1c)0 and 0d)81 and 0Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,a)25 and 1b)1 and 1c)0 and 0d)81 and 0Correct answer is option 'C'. Can you explain this answer?.
Solutions for A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,a)25 and 1b)1 and 1c)0 and 0d)81 and 0Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE.
Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,a)25 and 1b)1 and 1c)0 and 0d)81 and 0Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,a)25 and 1b)1 and 1c)0 and 0d)81 and 0Correct answer is option 'C'. Can you explain this answer?, a detailed solution for A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,a)25 and 1b)1 and 1c)0 and 0d)81 and 0Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,a)25 and 1b)1 and 1c)0 and 0d)81 and 0Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,a)25 and 1b)1 and 1c)0 and 0d)81 and 0Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice GATE tests.