GATE Exam  >  GATE Questions  >  A small project consists following activities... Start Learning for Free
A small project consists following activities. The relevant data about these activities is given below:

Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week is
    Correct answer is between '854,856'. Can you explain this answer?
    Verified Answer
    A small project consists following activities. The relevant data about...
    The resulting network is shown in figure.
    The critical path is 1-3-4-5 and duration = 18 week and the minimum duration = 12 week
    Total cost = 18×50 = 900 Rs.

    Activities lie on the critical path control the project duration so we can shorten the duration of these critical activities.
    The minimum cost of crashing out of (1-3), (3-4), (4-5) activities = 15 Rs per week
    Reduced the activities 3-4 by 1 week then the total cost = 17×50 + 15 = 865 Rs
    Now, there are two critical path viz. 1-3-4-5 and 1-4-5 and its project duration = 16 week
    Now there are two ways of reducing the duration of project further either reduce the activity duration (1-3) and (1-4) combined (crashing cost = 45 Rs. per week) or (1-4) and (3-4) combined (crashing cost = 40 Rs. per week). The minimum cost of crashing is in 2nd case.
    Total cost = 16×50 + 15+ 40 = 855 Rs.
    View all questions of this test
    Explore Courses for GATE exam

    Similar GATE Doubts

    A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer?
    Question Description
    A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer?.
    Solutions for A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
    Here you can find the meaning of A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer?, a detailed solution for A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer? has been provided alongside types of A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A small project consists following activities. The relevant data about these activities is given below:Overhead cost per week is 50 Rs. per week. Total cost of the project (in Rs.) if the project duration is reduced by 2 week isCorrect answer is between '854,856'. Can you explain this answer? tests, examples and also practice GATE tests.
    Explore Courses for GATE exam
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev