Question Description
Activity P is followed by Activity Q which in turn, is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below : Activity. Activity. Activity P. Q. R Duration. in days. 7 6 5 8 7 6 9 8 7 Direct Cost. 12 14 15 20 23 27 40 42 45 Rs. '000 For all the three activities taken together, the minimum possible direct cost for a total duration of 21 days will be a) Rs.81,000. b) Rs. 79,000 c) Rs. 78,000. d) Rs. 77,000? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared
according to
the GATE exam syllabus. Information about Activity P is followed by Activity Q which in turn, is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below : Activity. Activity. Activity P. Q. R Duration. in days. 7 6 5 8 7 6 9 8 7 Direct Cost. 12 14 15 20 23 27 40 42 45 Rs. '000 For all the three activities taken together, the minimum possible direct cost for a total duration of 21 days will be a) Rs.81,000. b) Rs. 79,000 c) Rs. 78,000. d) Rs. 77,000? covers all topics & solutions for GATE 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for Activity P is followed by Activity Q which in turn, is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below : Activity. Activity. Activity P. Q. R Duration. in days. 7 6 5 8 7 6 9 8 7 Direct Cost. 12 14 15 20 23 27 40 42 45 Rs. '000 For all the three activities taken together, the minimum possible direct cost for a total duration of 21 days will be a) Rs.81,000. b) Rs. 79,000 c) Rs. 78,000. d) Rs. 77,000?.
Solutions for Activity P is followed by Activity Q which in turn, is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below : Activity. Activity. Activity P. Q. R Duration. in days. 7 6 5 8 7 6 9 8 7 Direct Cost. 12 14 15 20 23 27 40 42 45 Rs. '000 For all the three activities taken together, the minimum possible direct cost for a total duration of 21 days will be a) Rs.81,000. b) Rs. 79,000 c) Rs. 78,000. d) Rs. 77,000? in English & in Hindi are available as part of our courses for GATE.
Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of Activity P is followed by Activity Q which in turn, is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below : Activity. Activity. Activity P. Q. R Duration. in days. 7 6 5 8 7 6 9 8 7 Direct Cost. 12 14 15 20 23 27 40 42 45 Rs. '000 For all the three activities taken together, the minimum possible direct cost for a total duration of 21 days will be a) Rs.81,000. b) Rs. 79,000 c) Rs. 78,000. d) Rs. 77,000? defined & explained in the simplest way possible. Besides giving the explanation of
Activity P is followed by Activity Q which in turn, is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below : Activity. Activity. Activity P. Q. R Duration. in days. 7 6 5 8 7 6 9 8 7 Direct Cost. 12 14 15 20 23 27 40 42 45 Rs. '000 For all the three activities taken together, the minimum possible direct cost for a total duration of 21 days will be a) Rs.81,000. b) Rs. 79,000 c) Rs. 78,000. d) Rs. 77,000?, a detailed solution for Activity P is followed by Activity Q which in turn, is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below : Activity. Activity. Activity P. Q. R Duration. in days. 7 6 5 8 7 6 9 8 7 Direct Cost. 12 14 15 20 23 27 40 42 45 Rs. '000 For all the three activities taken together, the minimum possible direct cost for a total duration of 21 days will be a) Rs.81,000. b) Rs. 79,000 c) Rs. 78,000. d) Rs. 77,000? has been provided alongside types of Activity P is followed by Activity Q which in turn, is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below : Activity. Activity. Activity P. Q. R Duration. in days. 7 6 5 8 7 6 9 8 7 Direct Cost. 12 14 15 20 23 27 40 42 45 Rs. '000 For all the three activities taken together, the minimum possible direct cost for a total duration of 21 days will be a) Rs.81,000. b) Rs. 79,000 c) Rs. 78,000. d) Rs. 77,000? theory, EduRev gives you an
ample number of questions to practice Activity P is followed by Activity Q which in turn, is followed by activity R. The direct cost of these activities in relation to the choice of feasible durations table is given below : Activity. Activity. Activity P. Q. R Duration. in days. 7 6 5 8 7 6 9 8 7 Direct Cost. 12 14 15 20 23 27 40 42 45 Rs. '000 For all the three activities taken together, the minimum possible direct cost for a total duration of 21 days will be a) Rs.81,000. b) Rs. 79,000 c) Rs. 78,000. d) Rs. 77,000? tests, examples and also practice GATE tests.