Question Description
In a network, a project activity has normal cost and normal duration of Rs. 400 and 8 days respectively. The same activity has crash cost and crash duration of Rs. 800 and 6 days. The crash cost slope of activity is;a)50b)100c)150d)200Correct answer is option 'D'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared
according to
the GATE exam syllabus. Information about In a network, a project activity has normal cost and normal duration of Rs. 400 and 8 days respectively. The same activity has crash cost and crash duration of Rs. 800 and 6 days. The crash cost slope of activity is;a)50b)100c)150d)200Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for In a network, a project activity has normal cost and normal duration of Rs. 400 and 8 days respectively. The same activity has crash cost and crash duration of Rs. 800 and 6 days. The crash cost slope of activity is;a)50b)100c)150d)200Correct answer is option 'D'. Can you explain this answer?.
Solutions for In a network, a project activity has normal cost and normal duration of Rs. 400 and 8 days respectively. The same activity has crash cost and crash duration of Rs. 800 and 6 days. The crash cost slope of activity is;a)50b)100c)150d)200Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE.
Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of In a network, a project activity has normal cost and normal duration of Rs. 400 and 8 days respectively. The same activity has crash cost and crash duration of Rs. 800 and 6 days. The crash cost slope of activity is;a)50b)100c)150d)200Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
In a network, a project activity has normal cost and normal duration of Rs. 400 and 8 days respectively. The same activity has crash cost and crash duration of Rs. 800 and 6 days. The crash cost slope of activity is;a)50b)100c)150d)200Correct answer is option 'D'. Can you explain this answer?, a detailed solution for In a network, a project activity has normal cost and normal duration of Rs. 400 and 8 days respectively. The same activity has crash cost and crash duration of Rs. 800 and 6 days. The crash cost slope of activity is;a)50b)100c)150d)200Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of In a network, a project activity has normal cost and normal duration of Rs. 400 and 8 days respectively. The same activity has crash cost and crash duration of Rs. 800 and 6 days. The crash cost slope of activity is;a)50b)100c)150d)200Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice In a network, a project activity has normal cost and normal duration of Rs. 400 and 8 days respectively. The same activity has crash cost and crash duration of Rs. 800 and 6 days. The crash cost slope of activity is;a)50b)100c)150d)200Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice GATE tests.