A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers was
  • a)
    55                            
  • b)
    100
  • c)
    50                            
  • d)
    110
  • e)
    None of these
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
A work could be completed in 100 days. Due to the absence of 10 worker...
Originally let there be x men.
Less men, More days     (Indirect Proportion)
Therefore, (x-10) : x  :: 100 :110
=> (x - 10) * 110 = x * 100    => x= 110
View all questions of this test
Most Upvoted Answer
A work could be completed in 100 days. Due to the absence of 10 worker...
Work was to be completed in 100days
so, 1 day work =1/100
in absence of 10 workers work =1/110
therefore,1/100-1/110*100=1/110
now on reversing as per rule no. of worker is 110.
Free Test
Community Answer
A work could be completed in 100 days. Due to the absence of 10 worker...
Given:
- A work can be completed in 100 days with a certain number of workers
- The work was completed in 110 days due to the absence of 10 workers

To find: The original number of workers

Solution:
Let the original number of workers be x.
According to the given information,

Work done by x workers in 1 day = 1/100
Work done by (x-10) workers in 1 day = 1/110

We know that the amount of work done is directly proportional to the number of workers and the time taken to complete the work. So we can set up the following equation:

(x)(100) = (x-10)(110)

Simplifying the equation,

100x = 110x - 1100
10x = 1100
x = 110

Therefore, the original number of workers was 110. Answer: (D)
Explore Courses for Quant exam
A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer?
Question Description
A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer?.
Solutions for A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A work could be completed in 100 days. Due to the absence of 10 workers it was completed in 110 days. The original number of workers wasa)55b)100c)50 d)110e)None of theseCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev