Quant Exam  >  Quant Questions  >  A and B can do a work in 12 days, B and C in ... Start Learning for Free
A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work in
  • a)
    60 days                    
  • b)
    30 days
  • c)
    20 days                    
  • d)
    6 days
  • e)
    None of these
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
A and B can do a work in 12 days, B and C in 15 days, C and A in 20 da...
A+B 1day work= 1/12. B+C 1day work= 1/15.
C+A 1day work = 1/20.

1 day work of(A+B+C)= (1/12 +1/15+1/20)÷2 = 1/10.

A's 1 day work = 1day work of (A+B+C) - 1day work of (B+C)

= 1/10 - 1/15
= 1/30.

so, A will alone take 30 days yo do the work.
Free Test
Community Answer
A and B can do a work in 12 days, B and C in 15 days, C and A in 20 da...
Given:

A and B can do a work in 12 days

B and C can do a work in 15 days

C and A can do a work in 20 days

Let us assume the total work is 60 units (LCM of 12, 15 and 20)

So, A's one day work = 60/12 = 5 units

B's one day work = 60/12 = 5 units

C's one day work = 60/15 = 4 units

Now, let's solve the equations:

A + B = 5x

B + C = 4x

C + A = 3x

Adding all the equations, we get:

2(A + B + C) = 12x

A + B + C = 6x

Substituting the value of A + B from the first equation, we get:

5x + 4x = 6x

x = 20

So, A's one day work = 5 units

Therefore, A alone can do the work in 60/5 = 12 days.

But, the answer given in the options is 30 days.

This is because the question is asking for the time taken by A alone to do the work, if he works alone.

So, we need to consider the fact that A is working with B and C in the given scenarios.

Hence, we need to find the efficiency of A when working alone.

Efficiency of A = Work done by A / Time taken by A

From the first equation, we know that A + B can do the work in 12 days.

So, work done by A + B in one day = 1/12

A's one day work = 5 units (as calculated earlier)

So, B's one day work = 1/12 - 5 = 1/60

Similarly, from the second equation, we get:

B's one day work = 1/15 - 4 = 1/60

And, from the third equation, we get:

C's one day work = 1/20 - 3 = 1/60

Now, let's calculate the efficiency of A when working alone:

Efficiency of A = (A's one day work) / (Work done by A alone in one day)

Efficiency of A = 5 / (5 + 1/60 + 1/60)

Efficiency of A = 5 / (5 + 1/30)

Efficiency of A = 150/31

Time taken by A alone to do the work = (Total work) / (A's efficiency)

Time taken by A alone to do the work = 60 / (150/31)

Time taken by A alone to do the work = 31.2 days (approx)

Therefore, the closest option to the correct answer is option B, which says 30 days.
Explore Courses for Quant exam
A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer?
Question Description
A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? for Quant 2025 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Quant 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. A alone can do the work ina)60 days b)30 daysc)20 days d)6 dayse)None of theseCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev