A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve is
  • a)
    3 MW
  • b)
    3.75 MW
  • c)
    6 MW
  • d)
    7.5 MW
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
A power plant has a maximum demand of 15 MW. The load factor is 50% an...
Load factor is the ratio of average load and maximum load and plant factor is the ratio of average load and plant capacity. Here average load will be 7.5KW and plant capacity will be 18.75KW so reserve will be 3.75KW

Free Test
Community Answer
A power plant has a maximum demand of 15 MW. The load factor is 50% an...
Given data:
Maximum demand = 15 MW
Load factor = 50%
Plant factor = 40%

Calculation:
1. Base Load:
Base load is the minimum level of power demand that occurs continuously in a power system.
Base Load = Maximum demand x Load factor
= 15 MW x 0.5
= 7.5 MW

2. Plant Capacity:
Plant capacity is the maximum power that can be generated by the power plant.
Plant Capacity = Maximum demand / Plant factor
= 15 MW / 0.4
= 37.5 MW

3. Operating Reserve:
Operating reserve is the amount of power that is available to meet the sudden increase in demand or in case of any emergency.
Operating Reserve = Plant Capacity - Maximum demand
= 37.5 MW - 15 MW
= 22.5 MW

But, the question asks for operating reserve based on the base load.
Operating Reserve = Plant Capacity - Base load
= 37.5 MW - 7.5 MW
= 30 MW x 0.25
= 7.5 MW

Therefore, the operating reserve is 7.5 MW.

Hence, option B is the correct answer.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer?
Question Description
A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? for Electrical Engineering (EE) 2025 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A power plant has a maximum demand of 15 MW. The load factor is 50% and the plant factoris 40%. The operating reserve isa)3 MWb)3.75 MWc)6 MWd)7.5 MWCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev