A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?
  • a)
    Rs. 24, Rs. 36
  • b)
    Rs. 30, Rs. 30
  • c)
    Rs. 20, Rs. 40
  • d)
    Rs. 25, Rs. 35
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
A and B can complete a piece of work in 10 days and 15 days respective...
A and B can complete a piece of work in 10 days and 15 days respectively,
Let total work be 60 units,
⇒ 1-day work of A = 6 units
⇒ 1-day work of B = 4 units
B starts the work and is joined by A after 5 days,
⇒ Work done by B in 5 days = 20 units,
⇒ Remaining work = 40 units which is done be A and B in the ratio of their efficiency
⇒ Work done by A = 24 units
⇒ Work done by B = 20 + 16 = 36 units
They earn a total of Rs. 60,
∴ Share of A = 24/60 × 60 = Rs. 24 and share of B = Rs. 36
View all questions of this test
Most Upvoted Answer
A and B can complete a piece of work in 10 days and 15 days respective...
Given information:

A can complete a piece of work in 10 days.

B can complete a piece of work in 15 days.

B starts the work and is joined by A after 5 days.

They earn a total of Rs. 60.


Approach:

We need to find the individual shares of A and B. To solve this problem, we can use the concept of work done by each person.


Solution:

Let's assume the total work to be done is 150 units (LCM of 10 and 15).

A's work efficiency = Total work / A's time = 150 / 10 = 15 units/day.

B's work efficiency = Total work / B's time = 150 / 15 = 10 units/day.


Work done by B in 5 days = B's work efficiency * 5 = 10 * 5 = 50 units.

Remaining work = Total work - Work done by B = 150 - 50 = 100 units.


A and B work together for the remaining 100 units of work.

Total time taken by A and B working together = Remaining work / (A's work efficiency + B's work efficiency) = 100 / (15 + 10) = 100 / 25 = 4 days.


Since B started the work 5 days earlier, the total time taken by B = 5 + 4 = 9 days.

Total time taken by A = 5 + 4 = 9 days.


A's share = (A's work efficiency * A's time) / Total time taken = (15 * 9) / 9 = 15 units.

B's share = (B's work efficiency * B's time) / Total time taken = (10 * 9) / 9 = 10 units.


To find the individual shares in terms of money, we can use the ratio of work done.

A's share in money = (A's work done / Total work) * Total money = (15 / 150) * 60 = Rs. 6.

B's share in money = (B's work done / Total work) * Total money = (10 / 150) * 60 = Rs. 4.


Therefore, A's share = Rs. 6 and B's share = Rs. 4, which is equivalent to Rs. 24 and Rs. 36 respectively. Hence, option A is the correct answer.
Explore Courses for SSC exam
A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer?
Question Description
A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer? for SSC 2024 is part of SSC preparation. The Question and answers have been prepared according to the SSC exam syllabus. Information about A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for SSC 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer?.
Solutions for A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC. Download more important topics, notes, lectures and mock test series for SSC Exam by signing up for free.
Here you can find the meaning of A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer?, a detailed solution for A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A and B can complete a piece of work in 10 days and 15 days respectively. B starts the work and is joined by A after 5 days. If they earn a total of Rs. 60, what are their individual shares?a)Rs. 24, Rs. 36b)Rs. 30, Rs. 30c)Rs. 20, Rs. 40d)Rs. 25, Rs. 35Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice SSC tests.
Explore Courses for SSC exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev