GATE Exam  >  GATE Questions  >  The precedence relations and duration (in day... Start Learning for Free
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are
  • a)
    0 and 4
  • b)
    1 and 4
  • c)
    2 and 3
  • d)
    3 and 1
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
The precedence relations and duration (in days) of activities of a pro...

Total Float = LFT – EFT =LST- EST
Where,
EST is the Earliest Short Time
EFT is Earliest Finish time
LST is Latest start time
And, LFT is Latest Finish time
View all questions of this test
Explore Courses for GATE exam

Similar GATE Doubts

The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer?
Question Description
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer?.
Solutions for The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer?, a detailed solution for The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, area)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev