GATE Exam  >  GATE Questions  >  A project consists of 7 jobs. Jobs A and F ca... Start Learning for Free
A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:
The expected completion time of the project is.
    Correct answer is '35'. Can you explain this answer?
    Verified Answer
    A project consists of 7 jobs. Jobs A and F can be started and complete...
    The critical path is A – B – D – E – G
    Therefore, the maximum completion time is 35 days.
    View all questions of this test
    Explore Courses for GATE exam
    A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer?
    Question Description
    A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer? for GATE 2024 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer? covers all topics & solutions for GATE 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer?.
    Solutions for A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
    Here you can find the meaning of A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer?, a detailed solution for A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer? has been provided alongside types of A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A project consists of 7 jobs. Jobs A and F can be started and completed independently. Jobs B and C can start only after job A has been completed. Jobs D, E and G can start only after jobs B, (C and D) and (E and F) are completed, respectively. Time estimates of all the jobs are given in the following table:The expected completion time of the project is.Correct answer is '35'. Can you explain this answer? tests, examples and also practice GATE tests.
    Explore Courses for GATE exam
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev